Knowledge Base:  
Portable Plural-Component Systems | Article 06 of 24 | How Proportioners Work
Last Updated: 10/01/2026
AirSprayTech Academy Portable Plural-Component Coating Systems Contractor Certificate Program

Portable Plural-Component Coating Systems for Contractors

Article 06 of 24

How Portable Proportioning Equipment Works

A plural-component proportioner is a coordinated material-delivery system. Its job is to receive the separate components, meter them in the specified relationship, condition and pressurize them as required, and deliver them to the approved mixing point without allowing the components to react inside the wrong part of the equipment.

The Central Principle

The proportioner meters components A and B. The mixing device combines them. The spray gun or applicator places the mixed material. These functions may be physically close together, but they remain separate technical operations.

Learning Objectives

After completing this article, you should be able to:

  • Identify the major sections of a portable proportioning system
  • Explain how positive-displacement pumps meter material
  • Compare fixed-ratio and electronically controlled proportioners
  • Explain the purpose of feed pumps, heaters, recirculation, and heated hoses
  • Describe the roles of sensors, alarms, valves, and controllers
  • Trace components A and B from their containers to the mixing point

A Proportioner Does Not Automatically Guarantee Correct Material

The machine can operate only within the limits of its setup, condition, calibration, material supply, temperature control, and monitoring system. A running pump and visible spray pattern do not independently prove that the material is correctly proportioned or completely mixed.

The Basic Material Path

Material containers → feed system → proportioning pumps → heaters and controls → separate A/B hoses → mix manifold or gun → mixer or mixing chamber → spray tip or applicator

The exact arrangement varies by equipment and coating. Some systems use gravity feed. Others use drum-mounted transfer pumps. Some heat both components independently. Others process materials at ambient temperature. The approved equipment and coating procedures determine the correct path.

The Major System Sections

1. Material Containers and Supply

Components may be supplied from pails, drums, totes, hoppers, or dedicated tanks. The supply section must keep the correct material connected to the correct side while preventing contamination, air ingestion, moisture intrusion, and interruption of flow.

2. Feed Pumps or Inlet Assemblies

Feed pumps move material from the containers to the proportioning pumps at a controlled inlet condition. They must supply enough material to prevent starvation without exceeding the proportioner's permitted inlet pressure.

3. Proportioning Pumps

Separate pumps meter components A and B. Their displacement, mechanical relationship, stroke measurement, or monitored flow establishes the delivered ratio according to the equipment design.

4. Drive System

The drive provides the force that moves the proportioning pumps. Portable systems may use pneumatic, hydraulic, electric, or engine-driven arrangements. The drive must provide stable operation through the required pressure and output range.

5. Material Conditioning

Agitators, circulation loops, drum heaters, primary heaters, and heated hoses may be used to bring each component into the required temperature and viscosity range.

6. Monitoring and Control

Gauges, pressure switches, temperature sensors, stroke sensors, flow meters, level devices, controllers, alarms, and automatic shutdowns may monitor the process and respond when operating limits are exceeded.

7. Separate A- and B-Side Delivery

Filters, check valves, pressure-relief devices, heaters, hoses, fittings, and shutoff valves carry the components separately to the approved mixing point.

8. Mixing and Application

The components enter a mix manifold, static mixer, impingement chamber, or other approved mixing assembly. The mixed material is then applied through the specified spray gun, tip, nozzle, or dispensing device.

9. Flushing System

A dedicated solvent or flushing-material pump may clean the mixed section before the material reacts. The separate A- and B-side sections may require different cleaning, storage, or preservation procedures.

Positive-Displacement Pumping

Many portable plural-component systems use positive-displacement pumps. For each complete operating cycle, a properly functioning pump displaces a predictable quantity of material based on its design and displacement.

If the A-side pump displaces twice the volume of the B-side pump during the same operating cycle, the mechanical arrangement may produce a nominal 2:1 relationship. Other ratios require different displacement relationships or controlled dosing methods.

The expected displacement assumes that the pump fills properly and that its valves, seals, packings, cylinder, and supply system are functioning correctly. Cavitation, leakage, worn components, blocked inlets, or trapped air can change actual delivery.

Pump Movement Is Not Enough

A pump rod can move without delivering its full expected volume. A starved inlet, leaking check valve, damaged seal, empty container, or cavitating feed pump can reduce delivery even though the machine continues to cycle.

Mechanically Linked Fixed-Ratio Systems

In a mechanically linked proportioner, the A- and B-side pumps are driven together. The relationship between their displacements establishes the nominal ratio. Two or more pump lowers may be connected to a common drive, yoke, beam, or linkage.

Advantages

  • Direct mechanical relationship between the pumps
  • Potentially rugged design for field work
  • Simplified operation for one established ratio
  • May require fewer electronic controls

Limitations

  • Ratio changes may require different pump sizes or mechanical parts
  • A mechanical connection does not detect every material-supply or pump problem
  • Actual output still requires calibration and ratio verification
  • Operator monitoring remains essential

Electronically Controlled Proportioning Systems

An electronically controlled system may monitor pump strokes, measured flow, pressure, valve timing, or a combination of operating data. The controller regulates component delivery according to the selected recipe or ratio.

Depending on the design, electronic controls may provide:

  • Adjustable mix ratios within an approved range
  • Recipe selection for different materials
  • Ratio, pressure, temperature, and flow monitoring
  • Pot-life timers and flushing programs
  • Alarm history and production records
  • Automatic interruption when programmed limits are exceeded
  • Password-protected setup and calibration functions

Electronic control adds useful information and protection, but it does not eliminate maintenance, physical inspection, ratio checks, operator training, or verification that the controller has been programmed correctly.

Stroke Measurement and Flow Measurement

Stroke-Based Monitoring

Sensors monitor pump movement. The controller uses the pump's calibrated displacement and recorded movement to calculate delivered quantity. This depends on accurate calibration and properly functioning pumps.

Flow-Meter-Based Monitoring

Flow meters measure material passing through the fluid circuit. Different metering technologies have different requirements involving viscosity, cleanliness, pressure, calibration, abrasiveness, and minimum flow.

Feed Pumps and Inlet Conditions

The proportioning pump cannot meter material that does not reach its inlet. High-viscosity products, long suction paths, cold material, restrictive inlet fittings, blocked strainers, and inadequate feed pumps can starve the proportioner.

A properly designed feed system should:

  • Maintain continuous material supply
  • Avoid air ingestion and cavitation
  • Stay within the proportioner's maximum inlet pressure
  • Use chemically compatible wetted components
  • Allow safe container changeover
  • Provide a method for identifying low level or empty containers

Feed pressure is not the same as spray pressure. Increasing inlet pressure beyond the equipment limit can damage the proportioning pump or alter its operation.

Heaters and Temperature Control

Primary heaters may raise component temperature before the material enters the delivery hose. Heated hoses help maintain the required temperature between the proportioner and application point.

Temperature control can affect:

  • Material viscosity and pressure loss
  • Feed-pump and proportioner performance
  • Mixing quality and atomization
  • Spray pattern and film build
  • Reaction rate, gel time, and cure

The operator should monitor actual material temperature—not merely the controller's set point. A heater setting does not prove that the material has reached or maintained the required temperature throughout the system.

Recirculation

Recirculation returns unmixed component material to its supply container or another approved point. It may be used to warm material, equalize temperature, remove trapped air, maintain suspension, or prepare the system for production.

Components A and B must remain in separate recirculation circuits. Return lines must never be crossed or placed in the wrong container. Recirculation pressure, flow, and duration must follow the equipment and coating manufacturer's instructions.

Cross-Contamination Can Cure Material Inside the Machine

A contaminated return line, shared tool, reversed hose, leaking valve, or incorrect container connection can introduce reactive material into the wrong side. Keep A-side and B-side tools, fittings, pumps, and containers clearly identified and separated.

Pressure Balance and Restrictions

The two material circuits may operate at different pressures because the components can have different viscosities, flow rates, pump sizes, hose diameters, filters, heaters, and restrictions.

An unexpected pressure difference can warn of a blocked filter, closed valve, cold material, empty container, feed problem, damaged hose, incorrect tip or chamber, or pump malfunction.

Pressure should be evaluated against the machine's normal operating relationship and approved alarm settings. Equal gauge readings do not prove correct ratio, and unequal readings do not automatically prove off-ratio operation.

Valves and Check Valves

Valves control the direction and timing of material flow. Depending on the system, they may:

  • Open or isolate material supply
  • Direct material to recirculation or spray
  • Prevent reverse flow
  • Control injection of the minor component
  • Introduce flushing material
  • Relieve trapped pressure through an approved path

A leaking check valve can permit backflow or inaccurate delivery. A valve that appears closed externally may still leak internally. Inspection, testing, cleaning, and replacement intervals are equipment-specific.

What the Controller Can—and Cannot—Do

The Controller May

  • Monitor programmed process values
  • Regulate valves or dosing
  • Track pump movement or material flow
  • Generate alarms and stop production
  • Store recipes and production information

The Controller Cannot

  • Identify every incorrectly labeled container
  • Repair a worn pump or leaking valve
  • Remove cured material from a passage
  • Correct an unsuitable coating selection
  • Replace trained operator judgment and inspection

Alarm Conditions

Depending on the equipment, alarms may address:

  • Ratio deviation
  • High or low pressure
  • Pressure imbalance between components
  • High or low material temperature
  • Pump runaway, stall, or dry running
  • Empty container or low material level
  • Pot-life expiration
  • Leak detection or unexpected valve activity
  • Electrical, air-supply, or controller faults

Every operator should know what each alarm means, whether the machine automatically stops, what material may have been applied, and what inspection or corrective action is required before restarting.

A Simplified Operating Sequence

  1. Verify component identity, ratio, and current documents
  2. Inspect containers, feed systems, pumps, heaters, hoses, controls, and guns
  3. Connect A and B to their correctly identified circuits
  4. Condition and recirculate the separate materials as required
  5. Prime the system and remove air according to the manual
  6. Calibrate and complete the required ratio verification
  7. Set approved temperatures, pressures, ratio, output, and alarm limits
  8. Direct the separate components to the mixing and application assembly
  9. Verify spray pattern, mixed-material condition, and film thickness
  10. Monitor material supply, pressures, temperatures, alarms, and application quality
  11. Flush, relieve pressure, shut down, and document the work as required

What the Contractor Must Verify

  • The proportioner is approved for the material and ratio
  • Pump output is adequate for the required spray assembly
  • Every fluid component has the required pressure and temperature rating
  • Wetted parts are chemically compatible with A, B, and flushing materials
  • Feed systems can supply both components without cavitation
  • Electrical power, compressed air, hydraulics, ventilation, and grounding are adequate
  • Calibration and ratio checks can be completed in the field
  • Replacement mixers, seals, filters, valves, tips, chambers, and service parts are available
  • Operators and maintenance personnel have received equipment-specific training

Key Takeaways

  • A proportioner meters components; it does not perform every mixing and application function
  • Positive-displacement pumps depend on proper filling, sealing, and valve operation
  • Fixed-ratio systems use established displacement relationships
  • Electronically controlled systems may regulate and monitor adjustable ratios
  • Feed pumps must prevent starvation without exceeding inlet limits
  • Heaters and heated hoses control viscosity and process temperature
  • Pressure readings are diagnostic information—not independent proof of ratio
  • Controls and alarms support trained operators; they do not replace them

Technical References

  • WAGNER TwinControl Electronically Controlled 2K Systems Operating Manual: System construction, pump configurations, operating principles, stroke measurement, calibration, feed pumps, heaters, controls, alarms, flushing, and maintenance. View the official manual
  • WAGNER TwinControl Product Information: Electronically monitored pump movement, ratio regulation, material valves, static mixing, process monitoring, and protective controls. View the official product information
  • Graco Hydra-Cat Fixed-Ratio Proportioning Pump Manual: Manufacturer information illustrating fixed-ratio positive-displacement pumps driven from a common power source. View the official manual
  • Graco XM Plural-Component Sprayer Instructions: Manufacturer guidance covering system installation, ratio selection, pressure balance, alarms, calibration, operation, flushing, troubleshooting, and maintenance. View the official manual

Plural-component equipment designs differ. Use the current manual, technical data, approved accessories, and training requirements for the exact make, model, configuration, and coating being used.

Professional responsibility: Never bypass an alarm, protective device, grounding requirement, pressure limit, temperature limit, or automatic shutdown to keep production moving. Stop the work, isolate the affected material, relieve pressure, determine the cause, and complete the required verification before restarting.

Copyright © 2026 Azimuth Spray Systems, LLC. All Rights Reserved.

No part of this material may be reproduced, distributed, transmitted, stored, or used in any form without prior written permission from Azimuth Spray Systems, LLC, except for brief quotations used with proper attribution.

AirSprayTech.com — The Finishing Authority®



Was this article helpful?

Comments:
 

Related Articles
 > Academy Series | Professional Certificate Programs
 > The Language of Finishing: A Paint and Coatings Industry Glossary
 > The Language of Finishing: Paint and Coatings Glossary A–B
 > The Language of Finishing: Paint and Coatings Glossary C–D
 > The Language of Finishing: Paint and Coatings Glossary E–F
 > The Language of Finishing: Paint and Coatings Glossary G–H
 > The Language of Finishing: Paint and Coatings Glossary I–K
 > The Language of Finishing: Paint and Coatings Glossary L–M
 > The Language of Finishing: Paint and Coatings Glossary N–O
 > The Language of Finishing: Paint and Coatings Glossary P–Q
 > The Language of Finishing: Paint and Coatings Glossary R
 > The Language of Finishing: Paint and Coatings Glossary S
 > The Language of Finishing: Paint and Coatings Glossary T
 > The Language of Finishing: Paint and Coatings Glossary U–V
 > The Language of Finishing: Paint and Coatings Glossary W–Z
 > The Language of Finishing: Coatings Standards and Acronyms
 > Airless Spraying - From Pump to Pattern
 > Airless Spraying—From Pump to Pattern | Article 01 of 18 How Airless Spray Equipment Works
 > Airless Spraying—From Pump to Pattern | Article 02 of 18 How to Read an Airless Spray Tip Number
 > Airless Spraying—From Pump to Pattern | Article 03 of 18 How to Choose the Correct Airless Tip Size
 > Airless Spraying—From Pump to Pattern | Article 04 of 18 Understanding Airless Fan Width and Orifice Size
 > Airless Spraying—From Pump to Pattern | Article 05 of 18 The Right Way to Set Airless Spray Pressure
 > Airless Spraying—From Pump to Pattern | Article 06 of 18 The Perfect Airless Spray Pattern
 > Airless Spraying—From Pump to Pattern | Article 07 of 18 Why an Airless Spray Pattern Develops Tails
 > Airless Spraying—From Pump to Pattern | Article 08 of 18 How Tip Wear Wastes Paint and Changes the Pattern
 > Airless Spraying—From Pump to Pattern | Article 09 of 18 Matching the Tip to the Sprayer’s Capacity
 > Airless Spraying—From Pump to Pattern | Article 10 of 18 How Airless Hose Size and Length Affect Performance
 > Airless Spraying—From Pump to Pattern | Article 11 of 18 How to Prime and Start an Airless Sprayer
 > Airless Spraying—From Pump to Pattern | Article 12 of 18 Professional Airless Spray-Gun Technique
 > Airless Spraying—From Pump to Pattern | Article 13 of 18 How to Shut Down, Flush, and Store an Airless Sprayer
 > Airless Spraying—From Pump to Pattern | Article 14 of 18 Airless Troubleshooting: When the Pump Will Not Prime
 > Airless Spraying—From Pump to Pattern | Article 15 of 18 Airless Troubleshooting: Surging, Pulsing, and Pressure Loss
 > Airless Spraying—From Pump to Pattern | Article 16 of 18 Electric, Gas, or Pneumatic Airless Equipment
 > Airless Spraying—From Pump to Pattern | Article 17 of 18 Choosing the Right Airless Sprayer for the Work
 > Airless Spraying—From Pump to Pattern | Article 18 of 18 Airless Safety: Understanding Injection-Injury Hazards
 > Airless Spraying-From Pump to Pattern Certificate of Completion
 > Airless Spraying—From Pump to Pattern | Final Assessment
 > Powder Coating - From Particle To Performance
 > Powder Coating—From Particle to Performance | Article 01 of 32 | The History of Powder Coating
 > Powder Coating—From Particle to Performance | Article 02 of 32 | What Powder Coating Is—and What It Is Not
 > Powder Coating—From Particle to Performance | Article 03 of 32 | What Is Inside a Powder Coating?
 > Powder Coating—From Particle to Performance | Article 04 of 32 | How Powder Coating Is Manufactured
 > Powder Coating—From Particle to Performance | Article 05 of 32 | Thermoset Versus Thermoplastic Powder Coatings
 > Powder Coating—From Particle to Performance | Article 06 of 32 | Epoxy, Polyester, and Epoxy-Polyester Hybrid Powders
 > Powder Coating—From Particle to Performance | Article 07 of 32 | Polyurethane, Acrylic, Fluoropolymer, and Specialty Powders
 > Powder Coating—From Particle to Performance | Article 08 of 32 | Selecting the Right Powder for the Application
 > Powder Coating—From Particle to Performance | Article 09 of 32 | Why Surface Preparation Determines Coating Performance
 > Powder Coating—From Particle to Performance | Article 10 of 32 | Preparing Steel, Aluminum, and Galvanized Surfaces
 > Powder Coating—From Particle to Performance | Article 11 of 32 | Mechanical Surface Preparation for Powder Coating
 > Powder Coating—From Particle to Performance | Article 12 of 32 | Chemical Pretreatment, Rinsing, and Dry-Off
 > Powder Coating—From Particle to Performance | Article 13 of 32 | How Electrostatic Powder Coating Works
 > Powder Coating—From Particle to Performance | Article 14 of 32 | Corona-Charging Powder Guns
 > Powder Coating—From Particle to Performance | Article 15 of 32 | Tribostatic Powder Application
 > Powder Coating—From Particle to Performance | Article 16 of 32 | Fluidized-Bed Powder Coating
 > Powder Coating—From Particle to Performance | Article 17 of 32: Anatomy of a Manual Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 18 of 32: Anatomy of an Automatic Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 20 of 32: Powder Feed, Recovery, Reclaim, and Color Change
 > Powder Coating—From Particle to Performance | Article 21 of 32: Compressed-Air Quality for Powder-Coating Equipment
 > Powder Coating—From Particle to Performance | Article 22 of 32: How to Set Up and Start a Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 23 of 32: Setting Powder Flow, Pattern Air, kV, and Current
 > Powder Coating—From Particle to Performance | Article 24 of 32: Professional Manual Powder-Gun Technique
 > Powder Coating—From Particle to Performance | Article 25 of 32: Setting Up Automatic Guns and Reciprocators
 > Powder Coating—From Particle to Performance | Article 26 of 32: Faraday-Cage Effect, Back Ionization, and Poor Coverage
 > Powder Coating—From Particle to Performance | Article 27 of 32: Curing Powder Coating—Time at Metal Temperature
 > Powder Coating—From Particle to Performance | Article 29 of 32: Measuring Powder-Coating Film Thickness
 > Powder Coating—From Particle to Performance | Article 30 of 32: Testing Adhesion, Cure, Gloss, Color, and Appearance
 > Powder Coating—From Particle to Performance | Article 31 of 32: Powder-Coating Defects and Corrective Action
 > Powder Coating—From Particle to Performance | Article 32 of 32: Powder-Coating Safety, Housekeeping, and Preventive Maintenance
 > Powder Coating—From Particle to Performance | Final Course Assessment
 > Powder Coating—From Particle to Performance | Certificate of Completion
 > Finishing Quality - From Spec to Sign-Off | AirSprayTech Academy
 > Finishing Quality—From Spec to Sign-Off | Article 01 of 28: Quality Begins with the Specification
 > Finishing Quality—From Spec to Sign-Off | Article 02 of 28: From Specification to Control Plan
 > Finishing Quality—From Spec to Sign-Off | Article 03 of 28: Document Control and Traceability
 > Finishing Quality—From Spec to Sign-Off | Article 04 of 28: Incoming Materials and Receiving Inspection
 > Finishing Quality—From Spec to Sign-Off | Article 05 of 28: Incoming Process Water Quality
 > Finishing Quality—From Spec to Sign-Off | Article 06 of 28: Process Water Treatment Systems
 > Finishing Quality—From Spec to Sign-Off | Article 07 of 28 Treating and Releasing Finishing Wastewater
 > Finishing Quality—From Spec to Sign-Off | Article 08 of 28: Surface Cleaning and Contamination Control
 > Finishing Quality—From Spec to Sign-Off | Article 09 of 28 Surface Pretreatment and Conversion Coating Control
 > Finishing Quality—From Spec to Sign-Off | Article 10 of 28 Coating Material Storage, Mixing, and Conditioning
 > Finishing Quality—From Spec to Sign-Off | Article 11 of 28 Compressed-Air Quality and System Control
 > Finishing Quality—From Spec to Sign-Off | Article 12 of 28 Temperature, Humidity, and Environmental Control
 > Finishing Quality—From Spec to Sign-Off | Article 13 of 28 Application Equipment Setup and Process Verification
 > Finishing Quality—From Spec to Sign-Off | Article 14 of 28 Wet-Film Thickness and Application Control
 > Finishing Quality—From Spec to Sign-Off | Article 15 of 28 Dry-Film Thickness Measurement and Control
 > Finishing Quality—From Spec to Sign-Off | Article 16 of 28 Cure Verification and Oven Performance
 > Finishing Quality—From Spec to Sign-Off | Article 17 of 28 Appearance, Color, Gloss, and Texture Inspection
 > Finishing Quality—From Spec to Sign-Off | Article 18 of 28 Coating Adhesion Testing and Interpretation
 > Finishing Quality—From Spec to Sign-Off | Article 19 of 28 Hardness, Impact, Flexibility, and Abrasion Testing
 > Finishing Quality—From Spec to Sign-Off | Article 20 of 28 Corrosion, Chemical, and Environmental Exposure Testing
 > Finishing Quality—From Spec to Sign-Off | Article 21 of 28 Holiday, Porosity, and Coating-Continuity Testing
 > Finishing Quality—From Spec to Sign-Off | Article 22 of 28 Building and Controlling the In-House Finishing Laboratory
 > Finishing Quality—From Spec to Sign-Off | Article 23 of 28 Sampling Plans and Inspection Frequency
 > Finishing Quality—From Spec to Sign-Off | Article 24 of 28 Building the Finishing Process Data Highway
 > Finishing Quality—From Spec to Sign-Off | Article 25 of 28 Nonconformance, Root Cause, and Corrective Action
 > Finishing Quality—From Spec to Sign-Off | Article 26 of 28 Final Product Audit, Acceptance, and Release
 > Finishing Quality—From Spec to Sign-Off | Article 27 of 28 Build a Quality Team That Includes the People Doing the Work
 > Finishing Quality—From Spec to Sign-Off | Article 28 of 28 Your Vendors Are Part of the Quality Team
 > Finishing Quality—From Spec to Sign-Off | Final Assessment
 > Finishing Quality—From Spec to Sign-Off | Certificate Request
 > Paint Shop Planning - From Floor Plan to First Spray
 > Paint Shop Planning—From Floor Plan to First Spray | Article 02 of 28 | Build a Project Team Before You Build the Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 03 of 28 | Meet the Authority Having Jurisdiction Early
 > Paint Shop Planning—From Floor Plan to First Spray | Article 04 of 28 | Creating the Owner’s Project Requirements
 > Paint Shop Planning—From Floor Plan to First Spray | Article 05 of 28 | Understanding NFPA 33 and Spray-Application Fire Protection
 > Paint Shop Planning—From Floor Plan to First Spray | Article 06 of 28 | Understanding the NEC in a Paint Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 07 of 28 | Flammable and Combustible Liquid Storage
 > Paint Shop Planning—From Floor Plan to First Spray | Article 08 of 28 | Building, Fire, and Mechanical Codes
 > Paint Shop Planning—From Floor Plan to First Spray | Article 09 of 28 | Environmental Permits and Emissions Planning
 > Paint Shop Planning—From Floor Plan to First Spray | Article 10 of 28 | Planning the Shop Layout and Product Flow
 > Paint Shop Planning—From Floor Plan to First Spray | Article 11 of 28 | Spray-Booth and Preparation-Station Selection
 > Paint Shop Planning—From Floor Plan to First Spray | Article 12 of 28 | Air-Makeup and Exhaust-System Planning
 > Paint Shop Planning—From Floor Plan to First Spray | Article 13 of 28 | Planning the Compressed-Air System
 > Paint Shop Planning—From Floor Plan to First Spray | Article 14 of 28 | Electrical Service, Controls, and Hazardous Locations
 > Paint Shop Planning—From Floor Plan to First Spray | Article 15 of 28 | Natural Gas, Heating, and Curing Requirements
 > Paint Shop Planning—From Floor Plan to First Spray | Article 16 of 28 | Fire Suppression, Detection, and Emergency Systems
 > Paint Shop Planning—From Floor Plan to First Spray | Article 17 of 28 | Writing an Equipment Specification Vendors Can Quote
 > Paint Shop Planning—From Floor Plan to First Spray | Article 18 of 28 | How to Compare Paint-Booth Proposals
 > Paint Shop Planning—From Floor Plan to First Spray | Article 19 of 28 | Who Is Responsible for What?
 > Paint Shop Planning—From Floor Plan to First Spray | Article 20 of 28 | Site Preparation and Construction Coordination
 > Paint Shop Planning—From Floor Plan to First Spray | Article 21 of 28 | Change Orders: Where Paint-Shop Budgets Go to Die
 > Paint Shop Planning—From Floor Plan to First Spray | Article 22 of 28 | Pre-Startup Inspection and Documentation
 > Paint Shop Planning—From Floor Plan to First Spray | Article 23 of 28 | Testing Booth Airflow and Pressure
 > Paint Shop Planning—From Floor Plan to First Spray | Article 24 of 28 | Testing Safety Interlocks and Emergency Controls
 > Paint Shop Planning—From Floor Plan to First Spray | Article 25 of 28 | Commissioning the Complete Paint Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 26 of 28 | Training Operators and Maintenance Personnel
 > Paint Shop Planning—From Floor Plan to First Spray | Article 27 of 28 | Final Acceptance: Do Not Sign Off Until It Performs
 > Paint Shop Planning—From Floor Plan to First Spray | Article 28 of 28 | Planning for Maintenance, Expansion, and the Next Ten Years
 > Paint Shop Planning—From Floor Plan to First Spray | Article 01 of 28 | Before You Buy a Booth: Define the Finishing Process
 > Paint Shop Planning—From Floor Plan to First Spray | Final Assessment
 > Paint Shop Planning—From Floor Plan to First Spray | Certificate of Completion Request
 > Automotive Refinish - From Repair Plan to Road Ready
 > Automotive Refinish—From Repair Plan to Road Ready | Article 01 of 28 | Start Before the Sandpaper: Vehicle Intake and Refinish Planning
 > Automotive Refinish—From Repair Plan to Road Ready | Article 02 of 28 | PPE Is Part of the Process: Protecting the Automotive Painter
 > Automotive Refinish—From Repair Plan to Road Ready | Article 03 of 28 | Fire, Fumes, and Ignition Sources: Everyday Refinish-Shop Safety
 > Automotive Refinish—From Repair Plan to Road Ready | Article 04 of 28 | A Clean Shop Paints Cleaner Cars: Housekeeping and Contamination Control
 > Automotive Refinish—From Repair Plan to Road Ready | Article 05 of 28 | Know What You Are Painting: Automotive Substrate Identification
 > Automotive Refinish—From Repair Plan to Road Ready | Article 06 of 28 | Clean Before You Cut: Washing, Degreasing, and Contamination Removal
 > Automotive Refinish—From Repair Plan to Road Ready | Article 07 of 28 | Stop Corrosion Before It Starts: Bare Metal and Corrosion Protection
 > Automotive Refinish—From Repair Plan to Road Ready | Article 08 of 28 | Sand With a Purpose: Abrasives, Grit Selection, and Surface Profiles
 > Automotive Refinish—From Repair Plan to Road Ready | Article 09 of 28 | Build It Straight: Fillers, Glazes, Primers, and Sealers
 > Automotive Refinish—From Repair Plan to Road Ready | Article 10 of 28 | Mask the Repair, Not the Mistake: Paper, Plastic, Tape, and Technique
 > Automotive Refinish—From Repair Plan to Road Ready | Article 11 of 28 | Choose the Complete System: Modern Automotive-Refinish Materials
 > Automotive Refinish—From Repair Plan to Road Ready | Article 12 of 28 | Control the Mix: Paint Storage, Mixing Rooms, and Material Management
 > Automotive Refinish—From Repair Plan to Road Ready | Article 13 of 28 | Match It Before You Spray It: Color Tools, Spray-Outs, and Color Acceptance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 14 of 28 | Choose the Right Spray Gun: Match the Equipment to the Finish
 > Automotive Refinish—From Repair Plan to Road Ready | Article 15 of 28 | Feed the Finish: Air-Compressor Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 16 of 28 | Keep the Gun Honest: Spray Equipment Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 17 of 28 | Paint With a Plan: Professional Basecoat and Clearcoat Application
 > Automotive Refinish—From Repair Plan to Road Ready | Article 18 of 28 | Control the Booth: Airflow, Filters, Lighting, and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 19 of 28 | Balance the Booth: Air-Makeup Unit Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 20 of 28 | Cure It by the Numbers: Flash, Bake, and Return-to-Service
 > Automotive Refinish—From Repair Plan to Road Ready | Article 21 of 28 | Correct Without Creating: Denibbing, Sanding, and Polishing
 > Automotive Refinish—From Repair Plan to Road Ready | Article 22 of 28 | Put It Back Right: Reassembly Without Damaging the Finish
 > Automotive Refinish—From Repair Plan to Road Ready | Article 23 of 28 | Inspect It Before the Customer Does: Final Quality Control
 > Automotive Refinish—From Repair Plan to Road Ready | Article 24 of 28 | Deliver More Than Shine: Customer Handoff and Fresh-Paint Care
 > Automotive Refinish—From Repair Plan to Road Ready | Article 25 of 28 | Control the Waste Stream: Paint, Solvent, Filters, and Compliance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 26 of 28 | Troubleshoot the Process: Find the Cause Before Repainting
 > Automotive Refinish—From Repair Plan to Road Ready | Article 27 of 28 | Make Quality Repeatable: Procedures, Training, and Team Accountability
 > Automotive Refinish—From Repair Plan to Road Ready | Article 28 of 28 | Road Ready Is Earned: Audit the Complete Refinish Process
 > Automotive Refinish—From Repair Plan to Road Ready | Final Assessment
 > Automotive Refinish—From Repair Plan to Road Ready | Certificate of Completion Request
 > Corrosion Protection for Industrial Coating Contractors - 00 Course Overview
 > Corrosion Protection for Industrial Coating Contractors - Article 01: Understanding Corrosion
 > Corrosion Protection for Industrial Coating Contractors - Article 02: Common Forms of Corrosion
 > Corrosion Protection for Industrial Coating Contractors - Article 03: Evaluating the Structure and Service Environment
 > Corrosion Protection for Industrial Coating Contractors - Article 04: Protective Coatings as the Primary Barrier
 > Corrosion Protection for Industrial Coating Contractors - Article 05: Selecting the Correct Coating System
 > Corrosion Protection for Industrial Coating Contractors - Article 06: Surface Cleanliness and Contaminant Testing
 > Corrosion Protection for Industrial Coating Contractors - Article 07: Abrasive Blasting and Surface-Preparation Standards
 > Corrosion Protection for Industrial Coating Contractors - Article 08: Surface Profile and Anchor Pattern
 > Corrosion Protection for Industrial Coating Contractors - Article 09: Environmental Conditions and Dew Point Control
 > Corrosion Protection for Industrial Coating Contractors - Article 10: Selecting Coating Systems for the Service Environment
 > Corrosion Protection for Industrial Coating Contractors - Article 11: Primers and Their Role in Corrosion Protection
 > Corrosion Protection for Industrial Coating Contractors - Article 12: Intermediate Coats, Finish Coats, and Stripe Coating
 > Corrosion Protection for Industrial Coating Contractors - Article 13: Coating Application Methods and Spray Technique
 > Corrosion Protection for Industrial Coating Contractors - Article 14: Coating Mixing, Thinning, Induction Time, and Pot Life
 > Corrosion Protection for Industrial Coating Contractors - Article 15: Wet Film and Dry Film Thickness Control
 > Corrosion Protection for Industrial Coating Contractors - Article 16: Holidays, Pinholes, and Discontinuity Testing
 > Corrosion Protection for Industrial Coating Contractors - Article 17: Coating Adhesion Testing and Failure Interpretation
 > Corrosion Protection for Industrial Coating Contractors - Article 18: Coating Defects and Failure Diagnosis
 > Corrosion Protection for Industrial Coating Contractors - Article 19: How Coatings and Cathodic Protection Work Together
 > Corrosion Protection for Industrial Coating Contractors - Article 20: Final Inspection, Repair Verification, and Project Documentation
 > Corrosion Protection for Industrial Coating Contractors - Final Assessment
 > Corrosion Protection for Industrial Coating Contractors - Final Certificate of Completion Request
 > Protective Linings for Industrial Coating Contractors | 00 - Course Overview
 > Protective Linings for Industrial Coating Contractors | Article 01 of 20 - Protective Linings: What They Are and Why They Fail
 > Protective Linings for Industrial Coating Contractors | Article 02 of 20 - Understanding the Lining Service Environment
 > Protective Linings for Industrial Coating Contractors | Article 04 of 20 - Selecting a Lining for the Material Being Contained
 > Protective Linings for Industrial Coating Contractors | Article 05 of 20 - Epoxy Linings and Where They Are Used
 > Protective Linings for Industrial Coating Contractors | Article 06 of 20 - Novolac Epoxy Linings for Severe Chemical Service
 > Protective Linings for Industrial Coating Contractors | Article 07 of 20 - Vinyl Ester and Polyester Lining Systems
 > Protective Linings for Industrial Coating Contractors | Article 08 of 20 - Polyurethane, Polyurea, and Elastomeric Linings
 > Protective Linings for Industrial Coating Contractors | Article 09 of 20 - Cementitious and Specialty Lining Systems
 > Protective Linings for Industrial Coating Contractors | Article 10 of 20 - Inspecting Steel and Concrete Before Lining Work Begins
 > Protective Linings for Industrial Coating Contractors | Article 11 of 20 - Preparing Steel for Protective-Lining Application
 > Protective Linings for Industrial Coating Contractors | Article 12 of 20 - Preparing Concrete for Protective Linings
 > Protective Linings for Industrial Coating Contractors | Article 13 of 20 - Moisture in Concrete: When a Lining Should Not Be Applied
 > Protective Linings for Industrial Coating Contractors | Article 14 of 20 - Environmental Conditions, Dew Point, and Condensation Control
 > Protective Linings for Industrial Coating Contractors | Article 15 of 20 - Mixing, Induction Time, Pot Life, and Material Temperature
 > Protective Linings for Industrial Coating Contractors | Article 16 of 20 - Applying High-Build and Plural-Component Linings
 > Protective Linings for Industrial Coating Contractors | Article 17 of 20 - Stripe Coating, Edges, Welds, Penetrations, and Difficult Areas
 > Protective Linings for Industrial Coating Contractors | Article 18 of 20 - Film Thickness, Recoat Windows, Curing, and Return to Service
 > Protective Linings for Industrial Coating Contractors | Article 19 of 20 - Inspecting Protective Linings
 > Protective Linings for Industrial Coating Contractors | Article 20 of 20 - Final Acceptance, Repairs, and Lining Maintenance
 > Protective Linings for Industrial Coating Contractors - Final Assessment
 > Protective Linings for Industrial Coating Contractors | Certificate of Completion Request
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | 00 - Course Overview
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 01 of 20 - Why Moisture Causes Coating and Flooring Fail
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 03 of 20 - Moisture Vapor Versus Hydrostatic Pressure
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 02 of 20 - How Moisture Moves Through Concrete
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 04 of 20 - Sources of Moisture in Concrete Slabs and Str
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 05 of 20 - Recognizing Moisture-Related Coating Failures
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 06 of 20 - Relative-Humidity Testing of Concrete Slabs
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 07 of 20 - Calcium-Chloride Moisture-Vapor-Emission Test
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 08 of 20 - Electronic Moisture Meters and Surface-Moistu
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 09 of 20 - Concrete pH and Alkalinity at the Bond Line
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 10 of 20 - Dew Point, Condensation, and Environmental Co
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 11 of 20 - Osmotic Blistering, Delamination, and Efflore
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 12 of 20 - When a Coating Should Not Be Applied
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 13 of 20 - Selecting a Moisture-Mitigation System
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 14 of 20 - Surface Preparation for Moisture-Mitigation M
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 15 of 20 - Applying Moisture-Mitigation Membranes
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 16 of 20 - Pinholes, Holidays, and Membrane Inspection
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 17 of 20 - Primers, Underlayments, Adhesives, and System
 > Moisture Vapor Management | 18 - Repairing Coating and Flooring Failures
 > Moisture Vapor Management | 19 - Documentation, Warranties, and Contractor Liability
 > Moisture Vapor Management | 20 - Complete Moisture-Management Plan
 > Moisture Vapor Management | Course Assessment
 > Moisture Vapor Management | Certificate Request
 > Commercial and Industrial Floor Coatings - Course Overview
 > Commercial and Industrial Floor Coatings | Article 01 of 24 | What Floor Coatings Must Do
 > Commercial and Industrial Floor Coatings | Article 02 of 24 | Defining the Service Environment
 > Commercial and Industrial Floor Coatings | Article 03 of 24 | Evaluating Existing Concrete and Previous Floors
 > Commercial and Industrial Floor Coatings | Article 04 of 24 | Concrete Moisture and Floor-Coating Failure
 > Commercial and Industrial Floor Coatings | Article 05 of 24 | Removing Oil, Grease and Chemical Contamination
 > Commercial and Industrial Floor Coatings | Article 06 of 24 | Mechanical Surface Preparation
 > Commercial and Industrial Floor Coatings | Article 07 of 24 | Concrete Surface Profile and Preparation Acceptance
 > Commercial and Industrial Floor Coatings | Article 08 of 24 | Repairing Cracks, Joints, Spalls and Damaged Concrete
 > Commercial and Industrial Floor Coatings | Article 09 of 24 | Primers, Patches, Underlayments and Moisture Mitigation
 > Commercial and Industrial Floor Coatings | Article 10 of 24 | Understanding Resinous Floor-Coating Chemistries
 > Commercial and Industrial Floor Coatings | Article 11 of 24 | Epoxy Floor-Coating Systems
 > Commercial and Industrial Floor Coatings | Article 12 of 24 | Polyurethane and Polyaspartic Floor Coatings
 > Commercial and Industrial Floor Coatings | Article 13 of 24 | Urethane-Cement Flooring for Heavy-Duty and Sanitary Service
 > Commercial and Industrial Floor Coatings | Article 14 of 24 | Methyl Methacrylate and Rapid-Return Flooring Systems
 > Commercial and Industrial Floor Coatings | Article 15 of 24 | Broadcast, Slurry, Mortar, and Self-Leveling Floor Systems
 > Commercial and Industrial Floor Coatings | Article 16 of 24 | Slip Resistance, Texture, Cleanability, and Appearance
 > Commercial and Industrial Floor Coatings | Article 17 of 24 | Coves, Drains, Penetrations, Edges, and Floor Transitions
 > Commercial and Industrial Floor Coatings | Article 18 of 24 | Mixing, Staging, Pot Life, and Installation Sequence
 > Commercial and Industrial Floor Coatings | Article 19 of 24 | Coverage, Film Thickness, Aggregate, and Material Control
 > Commercial and Industrial Floor Coatings | Article 20 of 24 | Environmental Conditions, Cure, Recoat Windows, and Return to Service
 > Commercial and Industrial Floor Coatings | Article 21 of 24 | Warehouse, Manufacturing, Vehicle and Aircraft-Hangar Floors
 > Commercial and Industrial Floor Coatings | Article 22 of 24 | Food, Beverage, Sanitary, Healthcare and Cleanroom Floors
 > Commercial and Industrial Floor Coatings | Article 23 of 24 | Inspection, Testing, Defects and Repairs
 > Commercial and Industrial Floor Coatings | Article 24 of 24 | Estimating, Documentation, Warranties, Maintenance and Final Acceptance
 > Commercial and Industrial Floor Coatings | Final Course Assessment
 > Commercial and Industrial Floor Coatings | Certificate of Completion Request
 > Commercial and Industrial Roof Coatings | 00 Certificate Program
 > Commercial and Industrial Roof Coatings | 01 of 25: What They Must Dand
 > Commercial and Industrial Roof Coatings | 02 of 25 | Coatings vs. Membranes
 > Commercial and Industrial Roof Coatings | 03 of 25 | Roof Assemblies and Substrates
 > Commercial and Industrial Roof Coatings | 04 of 25 | Reading the Specification
 > Commercial and Industrial Roof Coatings | 05 of 25 | Codes, Fire, Wind, and Energy
 > Commercial and Industrial Roof Coatings | 06 of 25 | New-Construction Readiness
 > Commercial and Industrial Roof Coatings | 07 of 25 | Restore or Replace
 > Commercial and Industrial Roof Coatings | 08 of 25 | Roof Moisture Surveys
 > Commercial and Industrial Roof Coatings | 09 of 25 | Drainage and Ponding Water
 > Commercial and Industrial Roof Coatings | 10 of 25 | Repairs Before Coating
 > Commercial and Industrial Roof Coatings | 11 of 25 | Cleaning and Contamination Removal
 > Commercial and Industrial Roof Coatings | 12 of 25 | Surface Preparation by Substrate
 > Commercial and Industrial Roof Coatings | 13 of 25 | Adhesion Testing
 > Commercial and Industrial Roof Coatings | 14 of 25 | Primers and Tie Coats
 > Commercial and Industrial Roof Coatings | 15 of 25 | Elastomeric Coatings
 > Commercial and Industrial Roof Coatings | 16 of 25 | Acrylic Systems
 > Commercial and Industrial Roof Coatings | 17 of 25 | Silicone Systems
 > Commercial and Industrial Roof Coatings | 18 of 25 | Polyurethane Systems
 > Commercial and Industrial Roof Coatings | 19 of 25 | PMMA Membranes
 > Commercial and Industrial Roof Coatings | 20 of 25 | Polyurea Membranes
 > Commercial and Industrial Roof Coatings | 21 of 25 | Spray Equipment
 > Commercial and Industrial Roof Coatings | 22 of 25 | Weather and Cure
 > Commercial and Industrial Roof Coatings | 23 of 25 | Inspection and Repairs
 > Commercial and Industrial Roof Coatings | 24 of 25 | Specifications and Warranties
 > Commercial and Industrial Roof Coatings | 25 of 25 | Technical Glossary
 > Commercial and Industrial Roof Coatings | Course Assessment
 > Commercial and Industrial Roof Coatings | Certificate Request
 > Professional Line Striping for Contractors | Course Overview
 > Professional Line Striping for Contractors | Article 01 of 24 | The Contractor’s Role
 > Professional Line Striping for Contractors | Article 02 of 24 | Plans, Specifications and Scope
 > Professional Line Striping for Contractors | Article 03 of 24 | Site Survey and Prejob Evaluation
 > Professional Line Striping for Contractors | Article 04 of 24 | MUTCD Marking Fundamentals
 > Professional Line Striping for Contractors | Article 05 of 24 | Accessible Parking Spaces
 > Professional Line Striping for Contractors | Article 06 of 24 | Fire Lanes and Restricted Areas
 > Professional Line Striping for Contractors | Article 07 of 24 | Parking-Lot Layout and Traffic Flow
 > Professional Line Striping for Contractors | Article 08 of 24 | Measuring and Layout Control
 > Professional Line Striping for Contractors | Article 09 of 24 | Pavement and Existing Markings
 > Professional Line Striping for Contractors | Article 10 of 24 | Surface Preparation and Marking Removal
 > Professional Line Striping for Contractors | Article 11 of 24 | Selecting Marking Materials
 > Professional Line Striping for Contractors | Article 12 of 24 | Marking Coating Chemistries
 > Professional Line Striping for Contractors | Article 13 of 24 | Glass Beads and Retroreflectivity
 > Professional Line Striping for Contractors | Article 14 of 24 | Striping Machines, Guns and Tips
 > Professional Line Striping for Contractors | Article 15 of 24 | Equipment Setup and Spray Control
 > Professional Line Striping for Contractors | Article 16 of 24 | Width, Thickness and Coverage
 > Professional Line Striping for Contractors | Article 17 of 24 | Stencils, Symbols and Arrows
 > Professional Line Striping for Contractors | Article 18 of 24 | Weather, Moisture, Drying and Cure
 > Professional Line Striping for Contractors | Article 19 of 24 | Work-Zone Traffic Control
 > Professional Line Striping for Contractors | Article 20 of 24 | Crew Positioning, Communication and PPE
 > Professional Line Striping for Contractors | Article 21 of 24 | Estimating Line Striping Work
 > Professional Line Striping for Contractors | Article 22 of 24 | Scheduling and Managing Crews
 > Professional Line Striping for Contractors | Article 23 of 24 | Inspection, Defects and Acceptance
 > Professional Line Striping for Contractors | Article 24 of 24 | Documentation, Maintenance and Growth
 > Professional Line Striping for Contractors | Course Assessment
 > Professional Line Striping for Contractors | Certificate Request
 > Academy Educational Standards and Editorial Policy
 > Secondary Containment Coating Systems | 00 Course Overview
 > Secondary Containment Coating Systems | Article 01 of 24 | Purpose and Responsibility
 > Secondary Containment Coating Systems | Article 02 of 24 | Defining the Service Environment
 > Secondary Containment Coating Systems | Article 03 of 24 | Chemical Exposure Variables
 > Secondary Containment Coating Systems | Article 04 of 24 | Concrete and Steel Structures
 > Secondary Containment Coating Systems | Article 06 of 24 | Concrete Moisture and Failure
 > Secondary Containment Coating Systems | Article 07 of 24 | Embedded Concrete Contamination
 > Secondary Containment Coating Systems | Article 08 of 24 | Mechanical Concrete Preparation
 > Secondary Containment Coating Systems | Article 09 of 24 | Steel Surface Preparation
 > Secondary Containment Coating Systems | Article 10 of 24 | Primers and Bonding Layers
 > Secondary Containment Coating Systems | Article 12 of 24 | Vinyl Ester Systems
 > Secondary Containment Coating Systems | Article 14 of 24 | Fiberglass-Reinforced Linings
 > Secondary Containment Coating Systems | Article 15 of 24 | Coves, Joints, Drains, and Penetrations
 > Secondary Containment Coating Systems | Article 16 of 24 | Mixing, Staging, and Pot Life
 > Secondary Containment Coating Systems | Article 17 of 24 | Application Methods and Equipment
 > Secondary Containment Coating Systems | Article 18 of 24 | Film Thickness and Continuity
 > Secondary Containment Coating Systems | Article 19 of 24 | Environmental Conditions and Cure
 > Secondary Containment Coating Systems | Article 20 of 24 | Inspection, Testing, and Final Acceptance
 > Secondary Containment Coating Systems | Article 21 of 24 | Defects, Failure Analysis, and Repairs
 > Secondary Containment Coating Systems | Article 22 of 24 | Spill Response and Return to Service
 > Secondary Containment Coating Systems | Article 23 of 24 | Inspection, Maintenance, and Service Life
 > Secondary Containment Coating Systems | Article 24 of 24 | Estimating and Contractor Responsibility
 > Secondary Containment Coating Systems | Course Assessment
 > Secondary Containment Coating Systems | Certificate of Completion Request
 > Portable Plural-Component Coating Systems | 00 Course Overview
 > Portable Plural-Component Systems | Article 01 of 24 | Understanding the System
 > Portable Plural-Component Systems | Article 02 of 24 | Ratios and Stoichiometry
 > Portable Plural-Component Systems | Article 03 of 24 | Pot Life and Cure
 > Portable Plural-Component Systems | Article 04 of 24 | Materials and Applications
 > Portable Plural-Component Systems | Article 05 of 24 | Reading the Documents
 > Portable Plural-Component Systems | Article 07 of 24 | Selecting a Proportioner
 > Portable Plural-Component Systems | Article 08 of 24 | Pails, Drums, Totes, and Feed Pumps
 > Portable Plural-Component Systems | Article 09 of 24 | Pumps and Ratio Control
 > Portable Plural-Component Systems | Article 10 of 24 | Material Conditioning
 > Portable Plural-Component Systems | Article 11 of 24 | Heating and Temperature Control
 > Portable Plural-Component Systems | Article 12 of 24 | Filters, Valves, Gauges, and Sensors
 > Portable Plural-Component Systems | Article 13 of 24 | Manifolds and Mixers
 > Portable Plural-Component Systems | Article 14 of 24 | Spray Guns, Tips, and Chambers
 > Portable Plural-Component Systems | Article 15 of 24 | Building a Mobile Rig
 > Portable Plural-Component Systems | Article 16 of 24 | Hoses and Connections
 > Portable Plural-Component Systems | Article 17 of 24 | Calibration and Ratio Testing
 > Portable Plural-Component Systems | Article 18 of 24 | Jobsite Setup and Startup
 > Portable Plural-Component Systems | Article 19 of 24 | Pressure and Spray Technique
 > Portable Plural-Component Systems | Article 20 of 24 | Film Thickness and Cure
 > Portable Plural-Component Systems | Article 21 of 24 | Correcting Off-Ratio Material
 > Portable Plural-Component Systems | Article 22 of 24 | Shutdown and Flushing
 > Portable Plural-Component Systems | Article 23 of 24 | Troubleshooting and Maintenance
 > Portable Plural-Component Systems | Article 24 of 24 | Final Acceptance
 > Portable Plural-Component Coating Systems | Course Assessment
 > Portable Plural-Component Systems | Certificate of Completion Request