Paint Shop Planning—From Floor Plan to First Spray

Article 08 of 28

Building, Fire, and Mechanical Codes

One paint shop. Several codes. No room for them to work separately.

A spray booth may arrive as one equipment package, but the building department does not see only a booth.

It may see a change in building use, a new industrial process, roof and wall penetrations, mechanical exhaust, fuel-fired equipment, electrical loads, hazardous materials, fire-protection requirements, and a workplace that employees must be able to enter and leave safely.

That means a paint-shop project may be reviewed under several codes by several officials. Each official may be looking at a different part of the same system.

The Practical Point

The booth, building, exhaust system, electrical installation, gas service, fire protection, and operating process must agree with one another. Passing one inspection does not automatically satisfy all the others.

Model Codes and Locally Adopted Codes

Organizations develop model codes that jurisdictions may adopt. A state, county, city, or other governmental authority may adopt a particular edition, modify it with local amendments, or enforce additional requirements.

Common model codes encountered during paint-shop planning include:

  • International Building Code
  • International Fire Code
  • International Mechanical Code
  • International Fuel Gas Code
  • International Plumbing Code
  • International Energy Conservation Code
  • National Electrical Code

The presence of a newer model-code edition on a publisher’s website does not mean that edition has been adopted for the project location. The project team must verify the applicable editions and local amendments with the Authorities Having Jurisdiction.

The Building Code: Can This Process Be Located Here?

The building code evaluates the structure and its use. A paint-shop project can affect the way the building is classified, arranged, protected, and occupied.

Occupancy and Use

The building official may evaluate the activity performed in the facility, the quantity and type of hazardous materials, the surrounding operations, and whether the proposed process changes the building’s occupancy classification or allowable use.

Installing a booth in an existing warehouse, automotive building, or manufacturing plant does not automatically mean the existing occupancy approval covers the new operation.

Construction and Fire Separation

The building code may affect wall construction, fire-resistance ratings, separation from other occupancies, openings, doors, penetrations, ceilings, and the relationship between the spray operation and the rest of the building.

A required fire-rated assembly can lose its intended protection when a duct, conduit, pipe, or access opening is installed without an approved penetration or protection method.

Means of Egress

Employees must be able to leave the building safely. Equipment placement can affect aisles, travel paths, exit access, exit doors, emergency lighting, signs, and required clearances.

A booth that fits the floor plan may still be unacceptable if it blocks an exit route or forces workers to travel through a hazardous area.

Structural Requirements

Roof-mounted air-makeup equipment, exhaust stacks, duct supports, pits, mezzanines, platforms, and suspended components may require structural evaluation.

The project must consider equipment weight, wind, weather, roof loading, seismic requirements where applicable, vibration, penetrations, support framing, and safe maintenance access.

Accessibility and Work Areas

Building alterations can trigger accessibility and work-area requirements. The project team should identify applicable routes, doors, controls, employee areas, and facility modifications during design.

The Fire Code: How Will Fire and Explosion Hazards Be Controlled?

The fire code addresses hazardous processes and materials in operating buildings. Spray finishing is commonly treated as a flammable-finishing operation requiring specific safeguards.

The fire authority may evaluate:

  • Spray-booth, spray-room, or spray-area construction
  • Equipment location and clearances
  • Mechanical ventilation
  • Electrical classification and ignition-source control
  • Fire suppression and alarm coordination
  • Flammable and combustible liquid storage
  • Paint-mixing and dispensing operations
  • Material quantities and storage arrangements
  • Heating, drying, and curing operations
  • Emergency shutdowns and safety interlocks
  • Housekeeping and overspray removal
  • Operating permits, inspections, and records

Operational Requirements Continue After Construction

Passing the final construction inspection is not the end of fire-code responsibility. The completed shop must continue to be operated and maintained safely.

Conditions that can create continuing violations include:

  • Blocked exits or equipment clearances
  • Excess paint or solvent stored in the work area
  • Unapproved portable electrical devices
  • Overloaded or poorly maintained filters
  • Accumulated overspray
  • Open waste or solvent containers
  • Disabled alarms or interlocks
  • Unapproved equipment modifications
  • Expired fire-protection inspections
  • Missing employee training and operating records

The Mechanical Code: Where Does the Air Go?

A paint booth may move a large quantity of air. The mechanical code and related requirements help govern how hazardous exhaust is captured, transported, discharged, and replaced.

Exhaust Air

The exhaust system must be designed for the process. The mechanical designer may need to evaluate airflow, fan selection, static pressure, filter resistance, duct construction, duct support, discharge velocity, exhaust termination, and access for inspection and cleaning.

Air Makeup

Air exhausted from the building must be replaced. Without properly planned replacement air, the building may become severely negative.

Negative building pressure can interfere with:

  • Booth airflow and finish quality
  • Opening exterior and interior doors
  • Operation of other exhaust systems
  • Fuel-burning appliances
  • Heating and air-conditioning performance
  • Dust and contaminant movement
  • Employee comfort

Exhaust Discharge Location

The discharge must be coordinated with property lines, roofs, openings, outdoor areas, neighboring buildings, and building air intakes.

A convenient place to cut a roof opening is not automatically an acceptable place to discharge paint-shop exhaust.

Duct Construction and Access

Hazardous exhaust ductwork may require particular materials, construction, joints, clearances, routing, supports, access openings, and fire-protection arrangements.

The design should avoid unnecessary pockets, ledges, or inaccessible areas where residue can accumulate. Inspection and cleaning access should be planned before the duct is installed.

The Fuel-Gas Code: Can the Building Feed the Burner?

Air-makeup units and curing systems may require substantial natural-gas or other fuel capacity. Seeing a gas pipe in the building does not prove that adequate fuel is available.

The qualified gas-system designer should verify:

  • Available fuel type
  • Required operating pressure
  • Total connected demand
  • Existing meter and regulator capacity
  • Pipe size and developed length
  • Simultaneous demand from other appliances
  • Combustion-air requirements
  • Venting requirements where applicable
  • Required shutoff valves and regulators
  • Testing, inspection, and startup requirements

The gas utility may need to upgrade the service, meter, or regulator. That conversation should happen before the air-makeup unit arrives.

The Plumbing Code: Be Careful With Drains

Paint-shop projects may involve sinks, wash areas, floor drains, water supplies, compressed-air drains, process water, and wastewater.

The presence of a floor drain does not mean paint, solvent, booth residue, wash water, or contaminated process water may be discharged into it.

The project team should determine:

  • What liquids the process may generate
  • Whether floor drains are permitted in specific areas
  • Where each drain discharges
  • Whether pretreatment or containment is required
  • Whether wastewater discharge approval is required
  • How spills will be contained
  • How compressor condensate will be managed
  • How contaminated liquids will be collected and disposed

The Energy Code: Exhausted Air Has a Price

A spray booth can exhaust large quantities of air that the building has already heated, cooled, or conditioned. The replacement air may also require substantial energy.

Energy-code and design considerations may include:

  • Air-makeup heating efficiency
  • Building-envelope penetrations
  • Duct and equipment insulation
  • Motor efficiency
  • Fan controls and operating schedules
  • Temperature controls
  • Building-pressure management
  • Heat recovery or recirculation where permitted
  • Automatic shutdown during unoccupied periods
  • Commissioning and control verification

Energy-saving changes must not defeat required ventilation, purge, temperature, or safety conditions.

The Electrical Code: Where Can Electrical Equipment Be Installed?

The NEC addresses electrical installation, including hazardous or classified locations associated with spray application.

Electrical planning must be coordinated with:

  • Coatings and solvents
  • Spray equipment and booth openings
  • Mechanical ventilation
  • Mixing, cleaning, and flash-off locations
  • Motors, lights, controls, and sensors
  • Fire-protection and emergency-shutdown systems
  • Grounding and bonding
  • Equipment listings and manufacturer instructions

Article 06 of this series provides a more detailed introduction to NEC planning for a paint shop.

NFPA Standards May Be Referenced

Building and fire codes may reference NFPA standards for particular systems, equipment, or hazards.

Commonly discussed subjects include:

  • Spray application using flammable or combustible materials
  • Flammable and combustible liquid storage
  • Electrical installations
  • Portable fire extinguishers
  • Automatic sprinkler systems
  • Fire-alarm systems
  • Drying and curing equipment
  • Combustible dust where applicable

The applicable standard, edition, and relationship to locally adopted codes must be confirmed by the qualified design team and AHJ.

One Project Can Require Several Permits

Do not assume a building permit covers every part of the paint shop.

Possible Permit or Approval Possible Subject
Building Occupancy, construction, structural work, exits, walls, roof openings, and equipment location
Fire Spray process, flammable materials, mixing, suppression, alarms, and operational approval
Mechanical Exhaust, air makeup, ductwork, heating, ventilation, and discharge
Electrical Service, wiring, hazardous locations, controls, lighting, motors, and interlocks
Fuel Gas Gas service, piping, regulators, combustion equipment, and testing
Plumbing Water supply, sinks, drains, interceptors, containment, and approved discharge
Environmental Air emissions, coating usage, hazardous waste, wastewater, and recordkeeping
Fire Protection Sprinkler or suppression drawings, calculations, installation, testing, and certification

Coordinate the Drawings

Each professional may prepare drawings for a particular discipline. Those drawings must describe one coordinated project.

Coordination should confirm:

  • The booth is in the same location on every drawing.
  • Equipment dimensions and service clearances agree.
  • Roof and wall penetrations are structurally supported.
  • Exhaust discharge does not conflict with outdoor air intakes.
  • Electrical-classification boundaries agree with booth openings and ventilation.
  • Fire-protection piping does not block lights, doors, filters, or service access.
  • Gas and electrical services match the selected equipment.
  • Exit paths remain open after all equipment is installed.
  • Control and emergency-shutdown functions are coordinated.
  • Maintenance personnel can reach equipment safely.

A Stack of Drawings Is Not Necessarily a Coordinated Design

If the electrical drawing, mechanical drawing, booth drawing, and fire-suppression drawing were prepared independently, the installation crew may become the first group to discover that four correct drawings do not fit in the same building.

Create a Code and Permit Matrix

The project manager should maintain a written matrix identifying each required review.

The matrix should include:

  • Reviewing department or authority
  • Applicable code and adopted edition
  • Local amendments
  • Required drawings and calculations
  • Responsible design professional
  • Permit or application number
  • Submission date
  • Review comments
  • Required corrections
  • Inspection stages
  • Final approval status

This prevents an approval from being forgotten because everyone assumed someone else was handling it.

Do Not Install From Preliminary Drawings

Preliminary drawings are useful for planning and pricing. They may not contain the information or approval required for construction.

Before field work begins, confirm:

  • The drawings are approved for construction.
  • Required professional seals and signatures are present.
  • AHJ review comments have been addressed.
  • Equipment submittals match the approved design.
  • The contractor has the latest drawing revision.
  • Changes are processed through a documented approval procedure.

Control Changes During Construction

Field conditions sometimes require changes. A duct encounters a structural member. A control panel must move. The gas service enters from another direction. The owner adds another piece of equipment.

A practical solution must still be reviewed for its effect on:

  • Building and structural requirements
  • Fire separation
  • Exhaust performance
  • Electrical classification
  • Equipment listings
  • Fire suppression
  • Service access
  • Permits and approved drawings
  • Testing and final acceptance

Do not allow an undocumented field decision to create an installation that no longer matches the approved plans.

Building, Fire, and Mechanical Planning Checklist

  • Confirm the applicable jurisdiction and reviewing departments.
  • Identify adopted code editions and local amendments.
  • Determine whether the project changes building use or occupancy.
  • Review equipment location, exits, access, and fire separation.
  • Complete required structural evaluation.
  • Coordinate exhaust, air makeup, and building pressure.
  • Confirm exhaust-discharge and outdoor-air-intake locations.
  • Verify electrical, gas, compressed-air, water, and drainage capacity.
  • Coordinate hazardous-location classification with ventilation.
  • Define fire-detection and suppression requirements.
  • Identify environmental permits and notifications.
  • Prepare coordinated construction drawings.
  • Create a permit and inspection matrix.
  • Control drawing revisions and field changes.
  • Obtain final approvals before production begins.

Planning and Code Notice

This article provides general educational information. It does not determine which codes apply to a particular project, provide a code analysis, or replace professional architectural and engineering services.

Building modifications, hazardous exhaust, electrical work, gas systems, fire protection, structural support, environmental compliance, and equipment installation must be evaluated and completed by qualified professionals.

Requirements vary by jurisdiction, building, process, materials, equipment, and adopted code editions. Obtain all required permits and approvals from the applicable Authorities Having Jurisdiction.

Authoritative Code Resources

These links illustrate model-code subject matter. The displayed edition may not be the edition adopted by the project’s jurisdiction.

The Bottom Line

A paint shop does not belong to one code or one inspector. It sits where building construction, fire safety, mechanical ventilation, electrical installation, fuel supply, environmental compliance, and daily operations meet.

Identify every authority. Confirm every adopted code. Coordinate the drawings. Track the permits. Control the changes. Inspect the work before it is covered, and obtain final approval before production begins.

The goal is not to collect permits for a file cabinet. The goal is to build a paint shop whose structure, utilities, safety systems, and operating process work together from the first spray onward.

Knowledge Check

  1. Why can several codes apply to one paint-shop project?
  2. What paint-shop concerns may be reviewed under the building code?
  3. Why must exhaust and air makeup be designed together?
  4. Why does a building permit not necessarily cover every required approval?
  5. What is the purpose of a code and permit matrix?
Next in the series:
Article 09 of 28—Environmental Permits and Emissions Planning


Was this article helpful?

Comments:
 

Related Articles
 > Academy Series | Professional Certificate Programs
 > Airless Spraying - From Pump to Pattern
 > Airless Spraying—From Pump to Pattern | Article 01 of 18 How Airless Spray Equipment Works
 > Airless Spraying—From Pump to Pattern | Article 02 of 18 How to Read an Airless Spray Tip Number
 > Airless Spraying—From Pump to Pattern | Article 03 of 18 How to Choose the Correct Airless Tip Size
 > Airless Spraying—From Pump to Pattern | Article 04 of 18 Understanding Airless Fan Width and Orifice Size
 > Airless Spraying—From Pump to Pattern | Article 05 of 18 The Right Way to Set Airless Spray Pressure
 > Airless Spraying—From Pump to Pattern | Article 06 of 18 The Perfect Airless Spray Pattern
 > Airless Spraying—From Pump to Pattern | Article 07 of 18 Why an Airless Spray Pattern Develops Tails
 > Airless Spraying—From Pump to Pattern | Article 08 of 18 How Tip Wear Wastes Paint and Changes the Pattern
 > Airless Spraying—From Pump to Pattern | Article 09 of 18 Matching the Tip to the Sprayer’s Capacity
 > Airless Spraying—From Pump to Pattern | Article 10 of 18 How Airless Hose Size and Length Affect Performance
 > Airless Spraying—From Pump to Pattern | Article 11 of 18 How to Prime and Start an Airless Sprayer
 > Airless Spraying—From Pump to Pattern | Article 12 of 18 Professional Airless Spray-Gun Technique
 > Airless Spraying—From Pump to Pattern | Article 13 of 18 How to Shut Down, Flush, and Store an Airless Sprayer
 > Airless Spraying—From Pump to Pattern | Article 14 of 18 Airless Troubleshooting: When the Pump Will Not Prime
 > Airless Spraying—From Pump to Pattern | Article 15 of 18 Airless Troubleshooting: Surging, Pulsing, and Pressure Loss
 > Airless Spraying—From Pump to Pattern | Article 16 of 18 Electric, Gas, or Pneumatic Airless Equipment
 > Airless Spraying—From Pump to Pattern | Article 17 of 18 Choosing the Right Airless Sprayer for the Work
 > Airless Spraying—From Pump to Pattern | Article 18 of 18 Airless Safety: Understanding Injection-Injury Hazards
 > Airless Spraying-From Pump to Pattern Certificate of Completion
 > Airless Spraying—From Pump to Pattern | Final Assessment
 > Powder Coating - From Particle To Performance
 > Powder Coating—From Particle to Performance | Article 01 of 32 | The History of Powder Coating
 > Powder Coating—From Particle to Performance | Article 02 of 32 | What Powder Coating Is—and What It Is Not
 > Powder Coating—From Particle to Performance | Article 03 of 32 | What Is Inside a Powder Coating?
 > Powder Coating—From Particle to Performance | Article 04 of 32 | How Powder Coating Is Manufactured
 > Powder Coating—From Particle to Performance | Article 05 of 32 | Thermoset Versus Thermoplastic Powder Coatings
 > Powder Coating—From Particle to Performance | Article 06 of 32 | Epoxy, Polyester, and Epoxy-Polyester Hybrid Powders
 > Powder Coating—From Particle to Performance | Article 07 of 32 | Polyurethane, Acrylic, Fluoropolymer, and Specialty Powders
 > Powder Coating—From Particle to Performance | Article 08 of 32 | Selecting the Right Powder for the Application
 > Powder Coating—From Particle to Performance | Article 09 of 32 | Why Surface Preparation Determines Coating Performance
 > Powder Coating—From Particle to Performance | Article 10 of 32 | Preparing Steel, Aluminum, and Galvanized Surfaces
 > Powder Coating—From Particle to Performance | Article 11 of 32 | Mechanical Surface Preparation for Powder Coating
 > Powder Coating—From Particle to Performance | Article 12 of 32 | Chemical Pretreatment, Rinsing, and Dry-Off
 > Powder Coating—From Particle to Performance | Article 13 of 32 | How Electrostatic Powder Coating Works
 > Powder Coating—From Particle to Performance | Article 14 of 32 | Corona-Charging Powder Guns
 > Powder Coating—From Particle to Performance | Article 15 of 32 | Tribostatic Powder Application
 > Powder Coating—From Particle to Performance | Article 16 of 32 | Fluidized-Bed Powder Coating
 > Powder Coating—From Particle to Performance | Article 17 of 32: Anatomy of a Manual Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 18 of 32: Anatomy of an Automatic Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 19 of 32: Powder Booths, Airflow, and Containment
 > Powder Coating—From Particle to Performance | Article 20 of 32: Powder Feed, Recovery, Reclaim, and Color Change
 > Powder Coating—From Particle to Performance | Article 21 of 32: Compressed-Air Quality for Powder-Coating Equipment
 > Powder Coating—From Particle to Performance | Article 22 of 32: How to Set Up and Start a Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 23 of 32: Setting Powder Flow, Pattern Air, kV, and Current
 > Powder Coating—From Particle to Performance | Article 24 of 32: Professional Manual Powder-Gun Technique
 > Powder Coating—From Particle to Performance | Article 25 of 32: Setting Up Automatic Guns and Reciprocators
 > Powder Coating—From Particle to Performance | Article 26 of 32: Faraday-Cage Effect, Back Ionization, and Poor Coverage
 > Powder Coating—From Particle to Performance | Article 27 of 32: Curing Powder Coating—Time at Metal Temperature
 > Powder Coating—From Particle to Performance | Article 28 of 32: Oven Profiling and Cure Verification
 > Powder Coating—From Particle to Performance | Article 29 of 32: Measuring Powder-Coating Film Thickness
 > Powder Coating—From Particle to Performance | Article 30 of 32: Testing Adhesion, Cure, Gloss, Color, and Appearance
 > Powder Coating—From Particle to Performance | Article 31 of 32: Powder-Coating Defects and Corrective Action
 > Powder Coating—From Particle to Performance | Article 32 of 32: Powder-Coating Safety, Housekeeping, and Preventive Maintenance
 > Powder Coating—From Particle to Performance | Final Course Assessment
 > Powder Coating—From Particle to Performance | Certificate of Completion
 > Powder Coating—From Particle to Performance | Request a Certificate of Completion
 > Finishing Quality - From Spec to Sign-Off | AirSprayTech Academy
 > Finishing Quality—From Spec to Sign-Off | Article 01 of 28: Quality Begins with the Specification
 > Finishing Quality—From Spec to Sign-Off | Article 02 of 28: From Specification to Control Plan
 > Finishing Quality—From Spec to Sign-Off | Article 03 of 28: Document Control and Traceability
 > Finishing Quality—From Spec to Sign-Off | Article 04 of 28: Incoming Materials and Receiving Inspection
 > Finishing Quality—From Spec to Sign-Off | Article 05 of 28: Incoming Process Water Quality
 > Finishing Quality—From Spec to Sign-Off | Article 06 of 28: Process Water Treatment Systems
 > Finishing Quality—From Spec to Sign-Off | Article 07 of 28 Treating and Releasing Finishing Wastewater
 > Finishing Quality—From Spec to Sign-Off | Article 08 of 28: Surface Cleaning and Contamination Control
 > Finishing Quality—From Spec to Sign-Off | Article 09 of 28 Surface Pretreatment and Conversion Coating Control
 > Finishing Quality—From Spec to Sign-Off | Article 10 of 28 Coating Material Storage, Mixing, and Conditioning
 > Finishing Quality—From Spec to Sign-Off | Article 11 of 28 Compressed-Air Quality and System Control
 > Finishing Quality—From Spec to Sign-Off | Article 12 of 28 Temperature, Humidity, and Environmental Control
 > Finishing Quality—From Spec to Sign-Off | Article 13 of 28 Application Equipment Setup and Process Verification
 > Finishing Quality—From Spec to Sign-Off | Article 14 of 28 Wet-Film Thickness and Application Control
 > Finishing Quality—From Spec to Sign-Off | Article 15 of 28 Dry-Film Thickness Measurement and Control
 > Finishing Quality—From Spec to Sign-Off | Article 16 of 28 Cure Verification and Oven Performance
 > Finishing Quality—From Spec to Sign-Off | Article 17 of 28 Appearance, Color, Gloss, and Texture Inspection
 > Finishing Quality—From Spec to Sign-Off | Article 18 of 28 Coating Adhesion Testing and Interpretation
 > Finishing Quality—From Spec to Sign-Off | Article 19 of 28 Hardness, Impact, Flexibility, and Abrasion Testing
 > Finishing Quality—From Spec to Sign-Off | Article 20 of 28 Corrosion, Chemical, and Environmental Exposure Testing
 > Finishing Quality—From Spec to Sign-Off | Article 21 of 28 Holiday, Porosity, and Coating-Continuity Testing
 > Finishing Quality—From Spec to Sign-Off | Article 22 of 28 Building and Controlling the In-House Finishing Laboratory
 > Finishing Quality—From Spec to Sign-Off | Article 23 of 28 Sampling Plans and Inspection Frequency
 > Finishing Quality—From Spec to Sign-Off | Article 24 of 28 Building the Finishing Process Data Highway
 > Finishing Quality—From Spec to Sign-Off | Article 25 of 28 Nonconformance, Root Cause, and Corrective Action
 > Finishing Quality—From Spec to Sign-Off | Article 26 of 28 Final Product Audit, Acceptance, and Release
 > Finishing Quality—From Spec to Sign-Off | Article 27 of 28 Build a Quality Team That Includes the People Doing the Work
 > Finishing Quality—From Spec to Sign-Off | Article 28 of 28 Your Vendors Are Part of the Quality Team
 > Finishing Quality—From Spec to Sign-Off | Final Assessment
 > Finishing Quality—From Spec to Sign-Off | Certificate Request
 > Paint Shop Planning - From Floor Plan to First Spray
 > Paint Shop Planning—From Floor Plan to First Spray | Article 02 of 28 | Build a Project Team Before You Build the Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 03 of 28 | Meet the Authority Having Jurisdiction Early
 > Paint Shop Planning—From Floor Plan to First Spray | Article 04 of 28 | Creating the Owner’s Project Requirements
 > Paint Shop Planning—From Floor Plan to First Spray | Article 05 of 28 | Understanding NFPA 33 and Spray-Application Fire Protection
 > Paint Shop Planning—From Floor Plan to First Spray | Article 06 of 28 | Understanding the NEC in a Paint Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 07 of 28 | Flammable and Combustible Liquid Storage
 > Paint Shop Planning—From Floor Plan to First Spray | Article 09 of 28 | Environmental Permits and Emissions Planning
 > Paint Shop Planning—From Floor Plan to First Spray | Article 10 of 28 | Planning the Shop Layout and Product Flow
 > Paint Shop Planning—From Floor Plan to First Spray | Article 11 of 28 | Spray-Booth and Preparation-Station Selection
 > Paint Shop Planning—From Floor Plan to First Spray | Article 12 of 28 | Air-Makeup and Exhaust-System Planning
 > Paint Shop Planning—From Floor Plan to First Spray | Article 13 of 28 | Planning the Compressed-Air System
 > Paint Shop Planning—From Floor Plan to First Spray | Article 14 of 28 | Electrical Service, Controls, and Hazardous Locations
 > Paint Shop Planning—From Floor Plan to First Spray | Article 15 of 28 | Natural Gas, Heating, and Curing Requirements
 > Paint Shop Planning—From Floor Plan to First Spray | Article 16 of 28 | Fire Suppression, Detection, and Emergency Systems
 > Paint Shop Planning—From Floor Plan to First Spray | Article 17 of 28 | Writing an Equipment Specification Vendors Can Quote
 > Paint Shop Planning—From Floor Plan to First Spray | Article 18 of 28 | How to Compare Paint-Booth Proposals
 > Paint Shop Planning—From Floor Plan to First Spray | Article 19 of 28 | Who Is Responsible for What?
 > Paint Shop Planning—From Floor Plan to First Spray | Article 20 of 28 | Site Preparation and Construction Coordination
 > Paint Shop Planning—From Floor Plan to First Spray | Article 21 of 28 | Change Orders: Where Paint-Shop Budgets Go to Die
 > Paint Shop Planning—From Floor Plan to First Spray | Article 22 of 28 | Pre-Startup Inspection and Documentation
 > Paint Shop Planning—From Floor Plan to First Spray | Article 23 of 28 | Testing Booth Airflow and Pressure
 > Paint Shop Planning—From Floor Plan to First Spray | Article 24 of 28 | Testing Safety Interlocks and Emergency Controls
 > Paint Shop Planning—From Floor Plan to First Spray | Article 25 of 28 | Commissioning the Complete Paint Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 26 of 28 | Training Operators and Maintenance Personnel
 > Paint Shop Planning—From Floor Plan to First Spray | Article 27 of 28 | Final Acceptance: Do Not Sign Off Until It Performs
 > Paint Shop Planning—From Floor Plan to First Spray | Article 28 of 28 | Planning for Maintenance, Expansion, and the Next Ten Years
 > Paint Shop Planning—From Floor Plan to First Spray | Article 01 of 28 | Before You Buy a Booth: Define the Finishing Process
 > Paint Shop Planning—From Floor Plan to First Spray | Final Assessment
 > Paint Shop Planning—From Floor Plan to First Spray | Certificate of Completion Request
 > Automotive Refinish - From Repair Plan to Road Ready
 > Automotive Refinish—From Repair Plan to Road Ready | Article 01 of 28 | Start Before the Sandpaper: Vehicle Intake and Refinish Planning
 > Automotive Refinish—From Repair Plan to Road Ready | Article 02 of 28 | PPE Is Part of the Process: Protecting the Automotive Painter
 > Automotive Refinish—From Repair Plan to Road Ready | Article 03 of 28 | Fire, Fumes, and Ignition Sources: Everyday Refinish-Shop Safety
 > Automotive Refinish—From Repair Plan to Road Ready | Article 04 of 28 | A Clean Shop Paints Cleaner Cars: Housekeeping and Contamination Control
 > Automotive Refinish—From Repair Plan to Road Ready | Article 05 of 28 | Know What You Are Painting: Automotive Substrate Identification
 > Automotive Refinish—From Repair Plan to Road Ready | Article 06 of 28 | Clean Before You Cut: Washing, Degreasing, and Contamination Removal
 > Automotive Refinish—From Repair Plan to Road Ready | Article 07 of 28 | Stop Corrosion Before It Starts: Bare Metal and Corrosion Protection
 > Automotive Refinish—From Repair Plan to Road Ready | Article 08 of 28 | Sand With a Purpose: Abrasives, Grit Selection, and Surface Profiles
 > Automotive Refinish—From Repair Plan to Road Ready | Article 09 of 28 | Build It Straight: Fillers, Glazes, Primers, and Sealers
 > Automotive Refinish—From Repair Plan to Road Ready | Article 10 of 28 | Mask the Repair, Not the Mistake: Paper, Plastic, Tape, and Technique
 > Automotive Refinish—From Repair Plan to Road Ready | Article 11 of 28 | Choose the Complete System: Modern Automotive-Refinish Materials
 > Automotive Refinish—From Repair Plan to Road Ready | Article 12 of 28 | Control the Mix: Paint Storage, Mixing Rooms, and Material Management
 > Automotive Refinish—From Repair Plan to Road Ready | Article 13 of 28 | Match It Before You Spray It: Color Tools, Spray-Outs, and Color Acceptance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 14 of 28 | Choose the Right Spray Gun: Match the Equipment to the Finish
 > Automotive Refinish—From Repair Plan to Road Ready | Article 15 of 28 | Feed the Finish: Air-Compressor Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 16 of 28 | Keep the Gun Honest: Spray Equipment Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 17 of 28 | Paint With a Plan: Professional Basecoat and Clearcoat Application
 > Automotive Refinish—From Repair Plan to Road Ready | Article 18 of 28 | Control the Booth: Airflow, Filters, Lighting, and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 19 of 28 | Balance the Booth: Air-Makeup Unit Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 20 of 28 | Cure It by the Numbers: Flash, Bake, and Return-to-Service
 > Automotive Refinish—From Repair Plan to Road Ready | Article 21 of 28 | Correct Without Creating: Denibbing, Sanding, and Polishing
 > Automotive Refinish—From Repair Plan to Road Ready | Article 22 of 28 | Put It Back Right: Reassembly Without Damaging the Finish
 > Automotive Refinish—From Repair Plan to Road Ready | Article 23 of 28 | Inspect It Before the Customer Does: Final Quality Control
 > Automotive Refinish—From Repair Plan to Road Ready | Article 24 of 28 | Deliver More Than Shine: Customer Handoff and Fresh-Paint Care
 > Automotive Refinish—From Repair Plan to Road Ready | Article 25 of 28 | Control the Waste Stream: Paint, Solvent, Filters, and Compliance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 26 of 28 | Troubleshoot the Process: Find the Cause Before Repainting
 > Automotive Refinish—From Repair Plan to Road Ready | Article 27 of 28 | Make Quality Repeatable: Procedures, Training, and Team Accountability
 > Automotive Refinish—From Repair Plan to Road Ready | Article 28 of 28 | Road Ready Is Earned: Audit the Complete Refinish Process
 > Automotive Refinish—From Repair Plan to Road Ready | Final Assessment
 > Automotive Refinish—From Repair Plan to Road Ready | Certificate of Completion Request
 > Corrosion Protection for Industrial Coating Contractors - 00 Course Overview
 > Corrosion Protection for Industrial Coating Contractors - Article 01: Understanding Corrosion
 > Corrosion Protection for Industrial Coating Contractors - Article 02: Common Forms of Corrosion
 > Corrosion Protection for Industrial Coating Contractors - Article 03: Evaluating the Structure and Service Environment
 > Corrosion Protection for Industrial Coating Contractors - Article 04: Protective Coatings as the Primary Barrier
 > Corrosion Protection for Industrial Coating Contractors - Article 05: Selecting the Correct Coating System
 > Corrosion Protection for Industrial Coating Contractors - Article 06: Surface Cleanliness and Contaminant Testing
 > Corrosion Protection for Industrial Coating Contractors - Article 07: Abrasive Blasting and Surface-Preparation Standards
 > Corrosion Protection for Industrial Coating Contractors - Article 08: Surface Profile and Anchor Pattern
 > Corrosion Protection for Industrial Coating Contractors - Article 09: Environmental Conditions and Dew Point Control
 > Corrosion Protection for Industrial Coating Contractors - Article 10: Selecting Coating Systems for the Service Environment
 > Corrosion Protection for Industrial Coating Contractors - Article 11: Primers and Their Role in Corrosion Protection
 > Corrosion Protection for Industrial Coating Contractors - Article 12: Intermediate Coats, Finish Coats, and Stripe Coating
 > Corrosion Protection for Industrial Coating Contractors - Article 13: Coating Application Methods and Spray Technique
 > Corrosion Protection for Industrial Coating Contractors - Article 14: Coating Mixing, Thinning, Induction Time, and Pot Life
 > Corrosion Protection for Industrial Coating Contractors - Article 15: Wet Film and Dry Film Thickness Control
 > Corrosion Protection for Industrial Coating Contractors - Article 16: Holidays, Pinholes, and Discontinuity Testing
 > Corrosion Protection for Industrial Coating Contractors - Article 17: Coating Adhesion Testing and Failure Interpretation
 > Corrosion Protection for Industrial Coating Contractors - Article 18: Coating Defects and Failure Diagnosis
 > Corrosion Protection for Industrial Coating Contractors - Article 19: How Coatings and Cathodic Protection Work Together
 > Corrosion Protection for Industrial Coating Contractors - Article 20: Final Inspection, Repair Verification, and Project Documentation
 > Corrosion Protection for Industrial Coating Contractors - Final Assessment
 > Corrosion Protection for Industrial Coating Contractors - Final Certificate of Completion Request
 > Protective Linings for Industrial Coating Contractors | 00 - Course Overview
 > Protective Linings for Industrial Coating Contractors | Article 01 of 20 - Protective Linings: What They Are and Why They Fail
 > Protective Linings for Industrial Coating Contractors | Article 02 of 20 - Understanding the Lining Service Environment
 > Protective Linings for Industrial Coating Contractors | Article 04 of 20 - Selecting a Lining for the Material Being Contained
 > Protective Linings for Industrial Coating Contractors | Article 05 of 20 - Epoxy Linings and Where They Are Used
 > Protective Linings for Industrial Coating Contractors | Article 06 of 20 - Novolac Epoxy Linings for Severe Chemical Service
 > Protective Linings for Industrial Coating Contractors | Article 07 of 20 - Vinyl Ester and Polyester Lining Systems
 > Protective Linings for Industrial Coating Contractors | Article 08 of 20 - Polyurethane, Polyurea, and Elastomeric Linings
 > Protective Linings for Industrial Coating Contractors | Article 09 of 20 - Cementitious and Specialty Lining Systems
 > Protective Linings for Industrial Coating Contractors | Article 10 of 20 - Inspecting Steel and Concrete Before Lining Work Begins
 > Protective Linings for Industrial Coating Contractors | Article 11 of 20 - Preparing Steel for Protective-Lining Application
 > Protective Linings for Industrial Coating Contractors | Article 12 of 20 - Preparing Concrete for Protective Linings
 > Protective Linings for Industrial Coating Contractors | Article 13 of 20 - Moisture in Concrete: When a Lining Should Not Be Applied
 > Protective Linings for Industrial Coating Contractors | Article 14 of 20 - Environmental Conditions, Dew Point, and Condensation Control
 > Protective Linings for Industrial Coating Contractors | Article 15 of 20 - Mixing, Induction Time, Pot Life, and Material Temperature
 > Protective Linings for Industrial Coating Contractors | Article 16 of 20 - Applying High-Build and Plural-Component Linings
 > Protective Linings for Industrial Coating Contractors | Article 17 of 20 - Stripe Coating, Edges, Welds, Penetrations, and Difficult Areas
 > Protective Linings for Industrial Coating Contractors | Article 18 of 20 - Film Thickness, Recoat Windows, Curing, and Return to Service
 > Protective Linings for Industrial Coating Contractors | Article 19 of 20 - Inspecting Protective Linings
 > Protective Linings for Industrial Coating Contractors | Article 20 of 20 - Final Acceptance, Repairs, and Lining Maintenance
 > Protective Linings for Industrial Coating Contractors - Final Assessment
 > Protective Linings for Industrial Coating Contractors | Certificate of Completion Request
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | 00 - Course Overview
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 01 of 20 - Why Moisture Causes Coating and Flooring Fail
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 03 of 20 - Moisture Vapor Versus Hydrostatic Pressure
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 02 of 20 - How Moisture Moves Through Concrete
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 04 of 20 - Sources of Moisture in Concrete Slabs and Str
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 05 of 20 - Recognizing Moisture-Related Coating Failures
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 06 of 20 - Relative-Humidity Testing of Concrete Slabs
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 07 of 20 - Calcium-Chloride Moisture-Vapor-Emission Test
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 08 of 20 - Electronic Moisture Meters and Surface-Moistu
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 09 of 20 - Concrete pH and Alkalinity at the Bond Line
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 10 of 20 - Dew Point, Condensation, and Environmental Co
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 11 of 20 - Osmotic Blistering, Delamination, and Efflore
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 12 of 20 - When a Coating Should Not Be Applied
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 13 of 20 - Selecting a Moisture-Mitigation System
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 14 of 20 - Surface Preparation for Moisture-Mitigation M
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 15 of 20 - Applying Moisture-Mitigation Membranes
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 16 of 20 - Pinholes, Holidays, and Membrane Inspection
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 17 of 20 - Primers, Underlayments, Adhesives, and System
 > Moisture Vapor Management | 18 - Repairing Coating and Flooring Failures
 > Moisture Vapor Management | 19 - Documentation, Warranties, and Contractor Liability
 > Moisture Vapor Management | 20 - Complete Moisture-Management Plan
 > Moisture Vapor Management | Course Assessment
 > Moisture Vapor Management | Certificate Request
 > Commercial and Industrial Floor Coatings - Course Overview
 > Commercial and Industrial Floor Coatings | Article 01 of 24 | What Floor Coatings Must Do
 > Commercial and Industrial Floor Coatings | Article 02 of 24 | Defining the Service Environment
 > Commercial and Industrial Floor Coatings | Article 03 of 24 | Evaluating Existing Concrete and Previous Floors
 > Commercial and Industrial Floor Coatings | Article 04 of 24 | Concrete Moisture and Floor-Coating Failure
 > Commercial and Industrial Floor Coatings | Article 05 of 24 | Removing Oil, Grease and Chemical Contamination
 > Commercial and Industrial Floor Coatings | Article 06 of 24 | Mechanical Surface Preparation
 > Commercial and Industrial Floor Coatings | Article 07 of 24 | Concrete Surface Profile and Preparation Acceptance
 > Commercial and Industrial Floor Coatings | Article 08 of 24 | Repairing Cracks, Joints, Spalls and Damaged Concrete
 > Commercial and Industrial Floor Coatings | Article 09 of 24 | Primers, Patches, Underlayments and Moisture Mitigation
 > Commercial and Industrial Floor Coatings | Article 10 of 24 | Understanding Resinous Floor-Coating Chemistries
 > Commercial and Industrial Floor Coatings | Article 11 of 24 | Epoxy Floor-Coating Systems
 > Commercial and Industrial Floor Coatings | Article 12 of 24 | Polyurethane and Polyaspartic Floor Coatings
 > Commercial and Industrial Floor Coatings | Article 13 of 24 | Urethane-Cement Flooring for Heavy-Duty and Sanitary Service
 > Commercial and Industrial Floor Coatings | Article 14 of 24 | Methyl Methacrylate and Rapid-Return Flooring Systems
 > Commercial and Industrial Floor Coatings | Article 15 of 24 | Broadcast, Slurry, Mortar, and Self-Leveling Floor Systems
 > Commercial and Industrial Floor Coatings | Article 16 of 24 | Slip Resistance, Texture, Cleanability, and Appearance
 > Commercial and Industrial Floor Coatings | Article 17 of 24 | Coves, Drains, Penetrations, Edges, and Floor Transitions
 > Commercial and Industrial Floor Coatings | Article 18 of 24 | Mixing, Staging, Pot Life, and Installation Sequence
 > Commercial and Industrial Floor Coatings | Article 19 of 24 | Coverage, Film Thickness, Aggregate, and Material Control
 > Commercial and Industrial Floor Coatings | Article 20 of 24 | Environmental Conditions, Cure, Recoat Windows, and Return to Service
 > Commercial and Industrial Floor Coatings | Article 21 of 24 | Warehouse, Manufacturing, Vehicle and Aircraft-Hangar Floors
 > Commercial and Industrial Floor Coatings | Article 22 of 24 | Food, Beverage, Sanitary, Healthcare and Cleanroom Floors
 > Commercial and Industrial Floor Coatings | Article 23 of 24 | Inspection, Testing, Defects and Repairs
 > Commercial and Industrial Floor Coatings | Article 24 of 24 | Estimating, Documentation, Warranties, Maintenance and Final Acceptance
 > Commercial and Industrial Floor Coatings | Final Course Assessment
 > Commercial and Industrial Floor Coatings | Certificate of Completion Request
 > Commercial and Industrial Roof Coatings | 00 Certificate Program
 > Commercial and Industrial Roof Coatings | 01 of 25: What They Must Dand
 > Commercial and Industrial Roof Coatings | 02 of 25 | Coatings vs. Membranes
 > Commercial and Industrial Roof Coatings | 03 of 25 | Roof Assemblies and Substrates
 > Commercial and Industrial Roof Coatings | 04 of 25 | Reading the Specification
 > Commercial and Industrial Roof Coatings | 05 of 25 | Codes, Fire, Wind, and Energy
 > Commercial and Industrial Roof Coatings | 06 of 25 | New-Construction Readiness
 > Commercial and Industrial Roof Coatings | 07 of 25 | Restore or Replace
 > Commercial and Industrial Roof Coatings | 08 of 25 | Roof Moisture Surveys
 > Commercial and Industrial Roof Coatings | 09 of 25 | Drainage and Ponding Water
 > Commercial and Industrial Roof Coatings | 10 of 25 | Repairs Before Coating
 > Commercial and Industrial Roof Coatings | 11 of 25 | Cleaning and Contamination Removal
 > Commercial and Industrial Roof Coatings | 12 of 25 | Surface Preparation by Substrate
 > Commercial and Industrial Roof Coatings | 13 of 25 | Adhesion Testing
 > Commercial and Industrial Roof Coatings | 14 of 25 | Primers and Tie Coats
 > Commercial and Industrial Roof Coatings | 15 of 25 | Elastomeric Coatings
 > Commercial and Industrial Roof Coatings | 16 of 25 | Acrylic Systems
 > Commercial and Industrial Roof Coatings | 17 of 25 | Silicone Systems
 > Commercial and Industrial Roof Coatings | 18 of 25 | Polyurethane Systems
 > Commercial and Industrial Roof Coatings | 19 of 25 | PMMA Membranes
 > Commercial and Industrial Roof Coatings | 20 of 25 | Polyurea Membranes
 > Commercial and Industrial Roof Coatings | 21 of 25 | Spray Equipment
 > Commercial and Industrial Roof Coatings | 22 of 25 | Weather and Cure
 > Commercial and Industrial Roof Coatings | 23 of 25 | Inspection and Repairs
 > Commercial and Industrial Roof Coatings | 24 of 25 | Specifications and Warranties
 > Commercial and Industrial Roof Coatings | 25 of 25 | Technical Glossary
 > Commercial and Industrial Roof Coatings | Course Assessment
 > Commercial and Industrial Roof Coatings | Certificate Request
 > Professional Line Striping for Contractors | Course Overview
 > Professional Line Striping for Contractors | Article 01 of 24 | The Contractor’s Role
 > Professional Line Striping for Contractors | Article 02 of 24 | Plans, Specifications and Scope
 > Professional Line Striping for Contractors | Article 03 of 24 | Site Survey and Prejob Evaluation
 > Professional Line Striping for Contractors | Article 04 of 24 | MUTCD Marking Fundamentals
 > Professional Line Striping for Contractors | Article 05 of 24 | Accessible Parking Spaces
 > Professional Line Striping for Contractors | Article 06 of 24 | Fire Lanes and Restricted Areas
 > Professional Line Striping for Contractors | Article 07 of 24 | Parking-Lot Layout and Traffic Flow
 > Professional Line Striping for Contractors | Article 08 of 24 | Measuring and Layout Control
 > Professional Line Striping for Contractors | Article 09 of 24 | Pavement and Existing Markings
 > Professional Line Striping for Contractors | Article 10 of 24 | Surface Preparation and Marking Removal
 > Professional Line Striping for Contractors | Article 11 of 24 | Selecting Marking Materials
 > Professional Line Striping for Contractors | Article 12 of 24 | Marking Coating Chemistries
 > Professional Line Striping for Contractors | Article 13 of 24 | Glass Beads and Retroreflectivity
 > Professional Line Striping for Contractors | Article 14 of 24 | Striping Machines, Guns and Tips
 > Professional Line Striping for Contractors | Article 15 of 24 | Equipment Setup and Spray Control
 > Professional Line Striping for Contractors | Article 16 of 24 | Width, Thickness and Coverage
 > Professional Line Striping for Contractors | Article 17 of 24 | Stencils, Symbols and Arrows
 > Professional Line Striping for Contractors | Article 18 of 24 | Weather, Moisture, Drying and Cure
 > Professional Line Striping for Contractors | Article 19 of 24 | Work-Zone Traffic Control
 > Professional Line Striping for Contractors | Article 20 of 24 | Crew Positioning, Communication and PPE
 > Professional Line Striping for Contractors | Article 21 of 24 | Estimating Line Striping Work
 > Professional Line Striping for Contractors | Article 22 of 24 | Scheduling and Managing Crews
 > Professional Line Striping for Contractors | Article 23 of 24 | Inspection, Defects and Acceptance
 > Professional Line Striping for Contractors | Article 24 of 24 | Documentation, Maintenance and Growth
 > Professional Line Striping for Contractors | Course Assessment
 > Professional Line Striping for Contractors | Certificate Request
 > Academy Educational Standards and Editorial Policy
 > Secondary Containment Coating Systems | 00 Course Overview
 > Secondary Containment Coating Systems | Article 01 of 24 | Purpose and Responsibility
 > Secondary Containment Coating Systems | Article 02 of 24 | Defining the Service Environment
 > Secondary Containment Coating Systems | Article 03 of 24 | Chemical Exposure Variables
 > Secondary Containment Coating Systems | Article 04 of 24 | Concrete and Steel Structures
 > Secondary Containment Coating Systems | Article 06 of 24 | Concrete Moisture and Failure
 > Secondary Containment Coating Systems | Article 07 of 24 | Embedded Concrete Contamination
 > Secondary Containment Coating Systems | Article 08 of 24 | Mechanical Concrete Preparation
 > Secondary Containment Coating Systems | Article 09 of 24 | Steel Surface Preparation
 > Secondary Containment Coating Systems | Article 10 of 24 | Primers and Bonding Layers
 > Secondary Containment Coating Systems | Article 12 of 24 | Vinyl Ester Systems
 > Secondary Containment Coating Systems | Article 14 of 24 | Fiberglass-Reinforced Linings
 > Secondary Containment Coating Systems | Article 15 of 24 | Coves, Joints, Drains, and Penetrations
 > Secondary Containment Coating Systems | Article 16 of 24 | Mixing, Staging, and Pot Life
 > Secondary Containment Coating Systems | Article 17 of 24 | Application Methods and Equipment
 > Secondary Containment Coating Systems | Article 18 of 24 | Film Thickness and Continuity
 > Secondary Containment Coating Systems | Article 19 of 24 | Environmental Conditions and Cure
 > Secondary Containment Coating Systems | Article 20 of 24 | Inspection, Testing, and Final Acceptance
 > Secondary Containment Coating Systems | Article 21 of 24 | Defects, Failure Analysis, and Repairs
 > Secondary Containment Coating Systems | Article 22 of 24 | Spill Response and Return to Service
 > Secondary Containment Coating Systems | Article 23 of 24 | Inspection, Maintenance, and Service Life
 > Secondary Containment Coating Systems | Article 24 of 24 | Estimating and Contractor Responsibility
 > Secondary Containment Coating Systems | Course Assessment
 > Secondary Containment Coating Systems | Certificate of Completion Request
 > Portable Plural-Component Coating Systems | 00 Course Overview
 > Portable Plural-Component Systems | Article 01 of 24 | Understanding the System
 > Portable Plural-Component Systems | Article 02 of 24 | Ratios and Stoichiometry
 > Portable Plural-Component Systems | Article 03 of 24 | Pot Life and Cure
 > Portable Plural-Component Systems | Article 04 of 24 | Materials and Applications
 > Portable Plural-Component Systems | Article 05 of 24 | Reading the Documents
 > Portable Plural-Component Systems | Article 06 of 24 | How Proportioners Work
 > Portable Plural-Component Systems | Article 07 of 24 | Selecting a Proportioner
 > Portable Plural-Component Systems | Article 08 of 24 | Pails, Drums, Totes, and Feed Pumps
 > Portable Plural-Component Systems | Article 09 of 24 | Pumps and Ratio Control
 > Portable Plural-Component Systems | Article 10 of 24 | Material Conditioning
 > Portable Plural-Component Systems | Article 11 of 24 | Heating and Temperature Control
 > Portable Plural-Component Systems | Article 12 of 24 | Filters, Valves, Gauges, and Sensors
 > Portable Plural-Component Systems | Article 13 of 24 | Manifolds and Mixers
 > Portable Plural-Component Systems | Article 14 of 24 | Spray Guns, Tips, and Chambers
 > Portable Plural-Component Systems | Article 15 of 24 | Building a Mobile Rig
 > Portable Plural-Component Systems | Article 16 of 24 | Hoses and Connections
 > Portable Plural-Component Systems | Article 17 of 24 | Calibration and Ratio Testing
 > Portable Plural-Component Systems | Article 18 of 24 | Jobsite Setup and Startup
 > Portable Plural-Component Systems | Article 19 of 24 | Pressure and Spray Technique
 > Portable Plural-Component Systems | Article 20 of 24 | Film Thickness and Cure
 > Portable Plural-Component Systems | Article 21 of 24 | Correcting Off-Ratio Material
 > Portable Plural-Component Systems | Article 22 of 24 | Shutdown and Flushing
 > Portable Plural-Component Systems | Article 23 of 24 | Troubleshooting and Maintenance
 > Portable Plural-Component Systems | Article 24 of 24 | Final Acceptance
 > Portable Plural-Component Coating Systems | Course Assessment
 > Portable Plural-Component Systems | Certificate of Completion Request
 > 2K and 3K Coating Systems | 00 Course Overview
 > 2K and 3K Coating Systems | Article 01 of 24: Understanding Production Systems
 > 2K and 3K Coating Systems | Article 02 of 24: Reactive Coating Chemistries
 > 2K and 3K Coating Systems | Article 03 of 24: Components A, B, and C
 > 2K and 3K Coating Systems | Article 04 of 24: Mixing Ratios and Tolerances
 > 2K and 3K Coating Systems | Article 05 of 24: Viscosity and Temperature
 > 2K and 3K Coating Systems | Article 06 of 24: Material Supply Systems
 > 2K and 3K Coating Systems | Article 07 of 24: Metering and Dosing
 > 2K and 3K Coating Systems | Article 08 of 24: Static and Dynamic Mixing
 > 2K and 3K Coating Systems | Article 09 of 24: Pot Life and Mixed Volume
 > 2K and 3K Coating Systems | Article 10 of 24: Flushing and Color Change
 > 2K and 3K Coating Systems | Article 11 of 24: Pressure and Flow Control
 > 2K and 3K Coating Systems | Article 12 of 24: Applicators and Atomization
 > 2K and 3K Coating Systems | Article 13 of 24: Color Change and Multiple-Hardener System Design
 > 2K and 3K Coating Systems | Article 14 of 24: Pot Life and Production Interruptions
 > 2K and 3K Coating Systems | Article 15 of 24: Calibration and Ratio Verification
 > 2K and 3K Coating Systems | Article 16 of 24: Flow, Pressure, Alarms, and Interlocks
 > 2K and 3K Coating Systems | Article 17 of 24: Startup, Production, and Shutdown
 > 2K and 3K Coating Systems | Article 18 of 24: Solvent and Waste Reduction
 > 2K and 3K Coating Systems | Article 19 of 24: Containing Off-Ratio Material
 > 2K and 3K Coating Systems | Article 20 of 24: Troubleshooting Ratio, Flow, Pressure, and Mixing Problems
 > 2K and 3K Coating Systems | Article 21 of 24: Production Operating Procedures
 > 2K and 3K Coating Systems | Article 22 of 24: Worker and Facility Safety
 > 2K and 3K Coating Systems | Article 23 of 24: Quality Control and Traceability
 > 2K and 3K Coating Systems | Article 24 of 24: System Acceptance and Lifecycle Management
 > 2K and 3K Coating Systems for OEM Product Finishers | Course Assessment
 > 2K and 3K Coating Systems | Certificate of Completion Request
 > Water and Wastewater Protective Coating Systems | 00 Course Overview
 > Water & Wastewater Coatings | Article 01 of 24: What Protective Systems Must Do
 > Water & Wastewater Coatings | Article 02 of 24: Mapping the Treatment Process
 > Water & Wastewater Coatings | Article 03 of 24: Defining Exposure Zones
 > Water & Wastewater Coatings | Article 04 of 24: Reading Project Requirements
 > Water & Wastewater Coatings | Article 05 of 24: Potable-Water Certification
 > Water & Wastewater Coatings | Article 06 of 24: Hydrogen Sulfide Corrosion
 > Water & Wastewater Coatings | Article 07 of 24: Evaluating Existing Concrete
 > Water & Wastewater Coatings | Article 08 of 24: Evaluating Existing Steel
 > Water and Wastewater Protective Coating Systems | Article 09 of 24: Cleaning and Decontamination
 > Water and Wastewater Protective Coating Systems | Article 10 of 24: Concrete Repair and Surface Rebuilding
 > Water and Wastewater Protective Coating Systems | Article 11 of 24: Concrete Surface Preparation
 > Water and Wastewater Protective Coating Systems | Article 12 of 24: Steel Surface Preparation
 > Water and Wastewater Protective Coating Systems | Article 13 of 24: Moisture and Environmental Control
 > Water and Wastewater Protective Coating Systems | Article 14 of 24: Confined-Space Safety
 > Water and Wastewater Protective Coating Systems | Article 15 of 24: Selecting Lining Chemistries
 > Water and Wastewater Protective Coating Systems | Article 16 of 24: Potable-Water Infrastructure
 > Water and Wastewater Protective Coating Systems | Article 17 of 24: High-Build Wastewater Linings
 > Water and Wastewater Protective Coating Systems | Article 18 of 24: Resurfacers, Mortars, and Membranes
 > Water and Wastewater Protective Coating Systems | Article 19 of 24: Cracks, Joints, and Transitions
 > Water and Wastewater Protective Coating Systems | Article 20 of 24: Material Storage, Mixing, Plural-Component Equipment, and Application Planning
 > Water and Wastewater Protective Coating Systems | Article 21 of 24: Inspection, Testing, and Quality-Control Documentation
 > Water and Wastewater Protective Coating Systems | Article 22 of 24: Defects, Failure Analysis, and Coating Repairs
 > Water and Wastewater Protective Coating Systems | Article 24 of 24: Estimating, Closeout, Warranties, and Lifecycle Maintenance
 > Water and Wastewater Protective Coating Systems Course Assessment
 > Water and Wastewater Protective Coating Systems | Certificate of Completion Request
 > Industrial Waterproofing | 00 Course Overview
 > Industrial Waterproofing | Article 01 of 24: What Systems Must Do
 > Industrial Waterproofing | Article 02 of 24: How Water Moves
 > Industrial Waterproofing | Article 03 of 24: Positive, Blind, and Negative Side
 > Industrial Waterproofing | Article 04 of 24: Define the Service Conditions
 > Industrial Waterproofing | Article 05 of 24: Reading Project Documents
 > Industrial Waterproofing | Article 06 of 24: Evaluating Concrete
 > Industrial Waterproofing | Article 07 of 24: Moisture and Hydrostatic Pressure
 > Industrial Waterproofing | Article 08 of 24: Concrete Surface Preparation
 > Industrial Waterproofing | Article 09 of 24: Cracks, Joints, and Penetrations
 > Industrial Waterproofing | Article 10 of 24: Primers and Bonding Layers
 > Industrial Waterproofing | Article 11 of 24: Membrane Chemistries
 > Industrial Waterproofing | Article 12 of 24: Storage, Mixing, and Proportioning
 > Industrial Waterproofing | Article 13 of 24: Membrane Application Methods
 > Industrial Waterproofing | Article 14 of 24: Thickness and Coverage Control
 > Industrial Waterproofing | Article 15 of 24: Cure and Recoat Windows
 > Industrial Waterproofing | Article 16 of 24: Below-Grade Structures
 > Industrial Waterproofing | Article 17 of 24: Plaza Decks and Podiums
 > Industrial Waterproofing | Article 18 of 24: Vaults and Utility Structures
 > Industrial Waterproofing | Article 19 of 24: Protection and Drainage
 > Industrial Waterproofing | Article 20 of 24: Inspection and Leak Detection
 > Industrial Waterproofing | Article 21 of 24: Defects and Repairs
 > Industrial Waterproofing | Article 22 of 24: Existing-System Rehabilitation
 > Industrial Waterproofing | Article 23 of 24: Estimating and Documentation
 > Industrial Waterproofing | Article 24 of 24: Acceptance and Maintenance
 > Industrial Waterproofing | Course Assessment
 > Industrial Waterproofing | Certificate of Completion Request
 > Masking and Surface Protection for Finishing Shops and Process Lines | 00: Course Overview
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 01 of 18: Masking Requirements: What Must Remain Uncoated—and Why
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 02 of 18: From Drawing or Repair Plan to Masking Instructions
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 03 of 18: Surface Condition, Compatibility, and Material Selection
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 04 of 18: Masking Tapes: General Purpose, Fine-Line, and Specialty Appl
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 05 of 18: Masking Papers, Plastic Films, and Overspray Sheeting
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 06 of 18: Caps, Plugs, and Sleeves: Protecting Part Features
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 07 of 18: Custom Masks, Die-Cuts, and Reusable Shields
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 08 of 18: Application Techniques: Edges, Seams, Curves, and Openings
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 09 of 18: Critical Features: Threads, Bores, Mating Faces, and Contact
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 10 of 18: Racks, Hooks, and Fixtures: Coordinating Support and Protecti
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 11 of 18: Masking for Liquid Coating Processes
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 12 of 18: Masking for Powder Coating and Oven-Cured Finishes
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 13 of 18: Masking Through Cleaning, Pretreatment, and Multistage Proces
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 14 of 18: Automotive Refinish: Vehicle Protection and Masking Through t
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 15 of 18: Job Shops: Managing Varied Parts, Short Runs, and Repeat Orde
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 16 of 18: OEM Process Lines: Standardizing Masking and Inspection
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 17 of 18: Troubleshooting Masking Failures
 > Masking and Surface Protection for Finishing Shops and Process Lines | Article 18 of 18: Mask Removal, Final Acceptance, and Process Improvement
 > Masking and Surface Protection for Finishing Shops and Process Lines | 19: Course Assessment
 > Masking and Surface Protection for Finishing Shops and Process Lines | 20: Certificate of Completion Request