AirSprayTech Academy Certificate Program
2K and 3K Coating Systems for OEM Product Finishers
Article 04 of 24
Mixing Ratios: Volume, Weight, and Allowable Tolerance
Mixing ratio is a controlled production requirement. Understanding
how the ratio is stated, measured, verified, and documented is
essential to producing a properly cured and repeatable coating film.
Learning Objectives
After completing this article, the reader should be able to:
- Interpret common 2K and 3K mixing-ratio expressions.
- Distinguish a ratio by volume from a ratio by weight.
- Explain why component density is required when converting between volume and weight.
- Understand how ratio tolerance affects coating performance.
- Recognize equipment and material conditions that can create off-ratio delivery.
- Describe practical methods for verifying and documenting proportioning accuracy.
The Mixing Ratio Is Part of the Coating Specification
A reactive coating is designed to cure when its components are
combined in a specified proportion. That proportion is not merely a
convenient equipment setting. It is part of the coating
manufacturer’s formulation and application requirements.
Too much or too little of one component can leave unreacted material
in the finished film. The coating may appear acceptable immediately
after application yet later exhibit poor hardness, brittleness,
softness, loss of adhesion, reduced chemical resistance, gloss
change, discoloration, or premature failure.
The approved ratio, ratio basis, allowable tolerance, and adjustment
authority must be established before production begins.
Reading a Two-Component Ratio
A ratio written as 4:1 normally means four parts of
the first identified component for every one part of the second
identified component. If the coating documentation defines
Component A first and Component B second, the ratio is:
4 parts Component A + 1 part Component B
Total mixed material = 5 parts
At 4:1, Component A represents 80 percent of the combined quantity
and Component B represents 20 percent.
A 10:1 ratio contains ten parts A and one part B, for a total of
eleven parts. Component B is therefore approximately 9.09 percent
of the total mixed quantity—not 10 percent.
Always confirm the order of the components. The notation 4:1 is
incomplete unless the responsible documents identify which
component is represented by each number.
Reading a Three-Component Ratio
A 3K coating can be expressed as a three-number ratio, such as
4:1:0.5. If the approved order is A:B:C, this means:
4 parts A + 1 part B + 0.5 part C
Total mixed material = 5.5 parts
Some equipment calculates the third component in relation to
Component A. Other equipment may calculate it in relation to the
A-and-B mixture, or as a percentage of the final mixture.
Those calculations are not automatically equivalent. The controller
configuration must match the exact method used by the coating
manufacturer and facility process specification.
Ratio by Volume Is Not Ratio by Weight
A volumetric proportioning system measures the amount of space
occupied by each liquid. A gravimetric system measures mass or
weight. The two ratios are identical only when the components have
the same density.
Coating components frequently have different densities because they
contain different resins, pigments, fillers, solvents, water, or
reactive materials. A gallon of Component A may therefore weigh
considerably more or less than a gallon of Component B.
Never enter a ratio stated by weight into equipment that meters by
volume—or the reverse—unless the ratio has been properly converted
using current, approved density data.
Density Makes the Conversion Possible
Density expresses the mass of a material per unit of volume. Common
coating-industry units include pounds per gallon, grams per
milliliter, and kilograms per liter.
Weight = Volume × Density
Assume a coating is specified at 4:1 by volume. Component A has a
density of 10 pounds per gallon, and Component B has a density of
8 pounds per gallon.
|
Component
|
Volume
|
Density
|
Calculated Weight
|
| A |
4 gallons |
10 lb/gal |
40 pounds |
| B |
1 gallon |
8 lb/gal |
8 pounds |
The equivalent weight relationship is 40:8, which simplifies to
5:1 by weight. The coating is still 4:1 by volume.
Both statements describe the same mixture using different
measurement bases.
Density values should come from current manufacturer documentation
or an approved test method. ASTM D1475 provides a recognized method
for determining the density of liquid coatings, inks, and related
components.
Do Not Make Unapproved Ratio Conversions
Density can vary with temperature, batch composition, pigment
loading, settling, solvent adjustment, and measurement technique.
Published values may be nominal rather than certified for a
particular batch.
A calculated conversion should not replace the coating
manufacturer’s approved ratio. When production equipment meters on
a different basis than the technical data sheet, obtain written
confirmation of the correct converted ratio and permissible
tolerance.
Document the densities, temperatures, units, calculation, source,
date, and person approving the conversion.
Understanding Ratio Tolerance
Ratio tolerance is the permitted variation from the target mixing
ratio. It should be provided by the coating manufacturer, process
specification, or responsible engineering authority.
A target ratio and an alarm setting are not necessarily the same.
The controller may use warning and shutdown limits that are tighter
than the coating’s maximum allowable variation. Tighter control can
provide time to stop the process before unacceptable material
reaches the product.
For example, the coating manufacturer may establish the largest
chemically acceptable variation, while the facility uses a narrower
production-control limit to protect quality. Those values and their
purposes should be clearly documented.
Do not select a tolerance merely because it is a convenient
controller default. The tolerance must reflect the coating,
equipment capability, product risk, and quality requirements.
Ratio Accuracy and Ratio Repeatability
Accuracy describes how closely the delivered ratio
agrees with the required ratio. Repeatability
describes how consistently the equipment reproduces its result.
A system can be repeatable but inaccurate. It may deliver nearly the
same mixture during every cycle while consistently delivering too
much hardener. It can also average the correct ratio over a long
period while producing short off-ratio portions during starts,
stops, flow changes, or valve transitions.
Production controls must consider both the accumulated ratio and the
quality of proportioning during actual operating conditions.
What Can Cause an Off-Ratio Condition?
|
Condition
|
Possible Effect
|
| Incorrect recipe |
The controller intentionally delivers the wrong proportion. |
| Incorrect meter factor |
Displayed flow differs from actual delivered volume. |
| Restricted filter or line |
One component cannot maintain the required flow or pressure. |
| Empty or low supply |
Air or interrupted material enters the component circuit. |
| Leaking dosing valve |
Material continues flowing when the valve should be closed. |
| Pressure imbalance |
Valve timing and component delivery become unstable. |
| Viscosity change |
Flow behavior changes because of temperature, settling, or solvent loss. |
| Worn meter or pump |
Actual displacement no longer agrees with the assumed value. |
| Flow outside the meter range |
Measurement accuracy may decline at excessively low or high flow. |
Dynamic Dosing and Flow Changes
Production flow is rarely constant. A robot accelerates and
decelerates, a reciprocator changes direction, guns trigger on and
off, and multiple applicators may operate independently.
Electronic dosing systems may monitor Component A flow and inject
measured quantities of Component B or C to maintain the programmed
ratio. The controls, meters, and valves must respond rapidly enough
to follow actual material demand.
A ratio test performed at one steady flow rate does not automatically
prove correct operation at minimum flow, maximum flow, rapid
triggering, or changing gun combinations. Commissioning should
challenge the system across the intended production range.
Ratio Verification Is a Controlled Test
Ratio verification measures the individual component quantities
delivered during a defined test. The equipment manufacturer’s
procedure must be followed because valve sequencing, pressure,
collection location, controller mode, and test duration affect the
result.
A sound ratio-check procedure should identify:
- The coating and recipe being tested.
- The required ratio and whether it is based on volume or weight.
- The approved collection point and equipment test mode.
- The material pressures, temperatures, and flow conditions.
- The containers, scales, or measuring devices used.
- The actual quantities collected and calculated result.
- The allowable tolerance and acceptance decision.
- The date, technician, and corrective action when required.
Ratio-check material should not be returned to the original supply
containers unless a written procedure specifically allows it.
Collected components may have been exposed to contamination,
moisture, or the opposite reactive material.
Ratio Monitoring Does Not Prove Complete Mixing
A proportioner can deliver the correct quantities while still
producing an inadequately mixed coating. Ratio control and mixing
quality are related, but they are different requirements.
Proper mixing also depends on component viscosity, temperature,
pressure balance, mixer design, mixer condition, flow rate, and the
location where the components enter the fluid stream.
The production process must verify both correct proportioning and
adequate homogenization. Article 08 of this course will examine
static and dynamic mixing in greater detail.
Responding to an Off-Ratio Alarm
An off-ratio alarm should trigger a defined response—not an
improvised adjustment. The response may include:
- Stop or inhibit coating application.
- Identify when the condition began.
- Quarantine potentially affected products.
- Check material supplies, pressures, filters, valves, meters, pumps, and controller settings.
- Correct the identified cause.
- Purge or flush suspect mixed material as required.
- Perform the approved ratio-verification test.
- Document the event and authorize production restart.
Repeatedly resetting an alarm without identifying its cause defeats
the quality control built into the system.
Key Takeaways
- The approved mixing ratio is a coating requirement, not merely an equipment setting.
- The order of A, B, and C must be clearly defined.
- A ratio by volume cannot be used as a ratio by weight without accounting for component density.
- ASTM D1475 is a recognized method for determining liquid-coating density.
- Ratio tolerances should come from coating and process requirements—not controller defaults.
- Accuracy and repeatability are related but different measurements of system performance.
- Ratio tests must follow the equipment manufacturer’s approved procedure.
- Correct proportioning does not by itself prove complete mixing.
Knowledge Check
-
In a 4:1 mixture, what percentage of the total is the one-part component?
-
Why can a 4:1 volume ratio produce a different numerical weight ratio?
-
Who should establish the allowable mixing-ratio tolerance?
-
Can a proportioning system be repeatable but inaccurate?
-
Does a correct ratio reading automatically prove that the components are thoroughly mixed?
Answer Guide
1. Twenty percent. The combined mixture contains five total parts.
2. The two components may have different densities.
3. The coating manufacturer, process specification, or responsible engineering authority.
4. Yes. It can repeatedly deliver nearly the same incorrect ratio.
5. No. Mixing quality must be evaluated separately from proportioning accuracy.
Technical References and Industry Resources
Manufacturer products are referenced as technical examples and not
as endorsements. Use the current manual, technical data sheet,
safety data sheet, approved recipe, and quality procedure for the
equipment and coating installed at the facility.
Professional responsibility: Do not change a
programmed ratio, ratio basis, meter factor, density value,
tolerance, catalyst percentage, or reducer percentage without
documented technical authorization. When coating, equipment, and
facility documents disagree, stop and obtain written clarification
before production continues.
Copyright © 2026 Azimuth Spray Systems, LLC. All Rights Reserved.
No part of this material may be reproduced, distributed,
transmitted, stored, or used in any form without prior written
permission from Azimuth Spray Systems, LLC, except for brief
quotations used with proper attribution.
AirSprayTech.com — The Finishing Authority®