Knowledge Base:  
Water and Wastewater Protective Coating Systems | Article 21 of 24: Inspection, Testing, and Quality-Control Documentation
Last Updated: 10/04/2026
AirSprayTech Academy Water and Wastewater Protective Coating Systems Certificate Program

AirSprayTech Academy Certificate Program

Water and Wastewater Protective Coating Systems

Article 21 of 24

Inspection, Testing, and Quality-Control Documentation

Verifying that the installed coating system meets the specification before the structure returns to service

Inspection Is Part of the Installation

Inspection is not something performed only after the coating work is complete. Effective quality control begins before surface preparation, continues through mixing and application, and ends only after the completed system has been tested, repaired, documented, and accepted.

The purpose of inspection is not to create paperwork or find fault with the crew. It is to identify conditions that could reduce service life while corrective action is still practical. The contractor, inspector, manufacturer, engineer, and facility owner should understand the acceptance criteria before work begins.

Establish the Inspection Plan Before Mobilization

The project specification and approved coating-system documents should define what will be inspected, how measurements will be taken, how frequently testing will occur, who will perform it, and what results constitute acceptance.

A practical inspection plan should identify:

  • The coating-system components and required thickness of each coat.
  • Specified surface cleanliness, profile, moisture, and substrate condition.
  • Environmental limitations and required measurement frequency.
  • Wet-film and dry-film thickness requirements.
  • Visual acceptance criteria for runs, sags, pinholes, overspray, contamination, and other defects.
  • Holiday-detection voltage, equipment, procedures, and acceptance limits.
  • Adhesion, cure, hardness, or other testing required by the specification.
  • Hold points that require approval before the next operation begins.
  • Repair, retesting, documentation, and final-acceptance procedures.

Testing should not be invented after the coating has been installed. Some tests are destructive, and some require test panels, witness areas, embedded instruments, or access that must be planned before application.

Contractor Quality Control and Independent Inspection

Contractor quality control and owner inspection are related, but they are not identical. The contractor remains responsible for controlling the work whether or not an independent inspector is present.

  • Quality control is performed by the contractor to keep the work within specification.
  • Quality assurance is performed for the owner or responsible authority to verify that the contractor's controls and completed work satisfy the contract.
  • Manufacturer observation may provide product-specific technical guidance but does not automatically replace the contractor's responsibility or the owner's inspection program.

Inspection responsibilities, authority, notification requirements, and reporting relationships should be defined in writing. An inspector should not direct unsafe work or make unauthorized changes to the coating system.

Verify Instruments Before Use

A reading is only useful when the instrument is appropriate for the test, functioning correctly, and used by a trained person. Before work begins, confirm the instrument's range, resolution, condition, calibration status, adjustment procedure, and compatibility with the substrate and coating.

  • Inspect probes, leads, batteries, cables, connectors, electrodes, and contact surfaces.
  • Use certified standards, shims, reference plates, or verification devices required by the test procedure.
  • Verify instruments at the required frequency and after suspected damage or abnormal readings.
  • Record the instrument manufacturer, model, serial number, calibration status, and verification results.
  • Protect instruments from contamination, moisture, impact, excessive heat, and improper storage.

Calibration, verification, and adjustment are not interchangeable terms. Follow the instrument manufacturer and referenced standard for the specific procedure being performed.

Environmental Inspection During Application

Environmental conditions can change rapidly inside tanks, clarifiers, galleries, process buildings, and outdoor structures. Readings taken only at the beginning of a shift may not represent the conditions present during the entire application.

Record, as applicable:

  • Air temperature.
  • Substrate temperature.
  • Relative humidity.
  • Calculated or instrument-reported dew-point temperature.
  • The difference between substrate temperature and dew point.
  • Ventilation status, airflow, weather conditions, and evidence of condensation.

Readings should be taken near the actual work surface and repeated at the frequency required by the specification, whenever conditions change, and before application resumes after an interruption.

Visual Inspection

Visual inspection should be performed after each coat and before the next coat conceals the work. Adequate lighting and access are essential. Inspectors should view the surface from multiple directions because low-angle lighting can reveal defects that are difficult to see under general illumination.

Look for:

  • Pinholes, holidays, voids, craters, fisheyes, and porosity.
  • Runs, sags, curtains, puddles, and excessive buildup.
  • Dry spray, overspray, rough texture, poor flow, or insufficient coverage.
  • Blisters, bubbles, swelling, lifting, wrinkling, checking, or cracking.
  • Contamination, insects, debris, water marks, or foreign material.
  • Incomplete stripe coating at welds, edges, bolts, penetrations, and difficult geometry.
  • Missed areas, thin areas, color variation, or incomplete hiding.
  • Poorly formed terminations, transitions, coves, seams, and repair boundaries.

Mark defects using a method that does not damage or contaminate the coating. Solvent markers, wax crayons, and incompatible tapes should not be used unless approved.

Wet-Film Thickness

Wet-film thickness measurements give the applicator immediate information while the coating can still be adjusted. A wet-film gauge is pressed into the freshly applied material, and the reading is interpreted according to the gauge instructions.

The theoretical relationship between wet-film thickness and dry-film thickness depends on the coating's volume solids:

Estimated DFT = WFT × Volume Solids as a Decimal

For example, a coating with 80 percent volume solids applied at 20 mils wet would theoretically produce approximately 16 mils dry before considering thinning, surface profile, transfer loss, measurement variation, or other field factors.

Wet-film testing may not be practical for extremely fast-reacting materials, heavily textured coatings, aggregate-filled systems, or surfaces where contact would disturb the film. Follow the product and project requirements.

Dry-Film Thickness on Steel

Nondestructive dry-film thickness gauges are commonly used on coated steel. ASTM D7091 addresses the use of magnetic and eddy-current gauges, while AMPP/SSPC-PA 2 establishes procedures for determining conformance with specified thickness ranges on metal substrates.

The inspector must understand the difference between an individual gauge reading, a spot measurement, and an area measurement. Acceptance is normally based on the sampling plan and permitted ranges established by the specification—not on selecting only the highest or lowest readings.

  • Verify the gauge on an uncoated substrate or an approved reference surface.
  • Account for the effect of abrasive-blast surface profile.
  • Take readings at the specified number and distribution of locations.
  • Include difficult geometry, edges, welds, repairs, and suspected thin areas when appropriate.
  • Record individual readings and required calculated averages.

Thickness on Concrete Requires a Defined Method

Conventional magnetic dry-film gauges do not measure coating thickness directly on concrete. Thickness may instead be controlled through wet-film measurements, material consumption, depth gauges, test panels, embedded references, drilled or cut samples, ultrasonic methods approved for the system, or other specified procedures.

Concrete texture, porosity, bugholes, repairs, high spots, and profile variation make thickness interpretation more difficult. The measurement method and acceptance criteria must be agreed upon before application.

Material Consumption as a Quality-Control Tool

Material usage should be compared with the coated area and the manufacturer's theoretical coverage. This comparison cannot replace direct thickness measurements, but it can reveal a significant discrepancy that deserves investigation.

The calculation should consider:

  • Actual surface area, including structural details and difficult geometry.
  • Specified thickness and product volume solids.
  • Surface profile and concrete porosity.
  • Material remaining in containers, hoses, pumps, filters, and mixing equipment.
  • Overspray, waste, spillage, test spraying, and discarded mixed material.
  • Material used for stripe coats, repairs, and reinforcement.

Unexpectedly low consumption may indicate insufficient thickness or missed areas. Unexpectedly high consumption may indicate excessive buildup, inaccurate area calculations, abnormal waste, or poor transfer efficiency.

Holiday Detection on Conductive Substrates

Holiday detection locates discontinuities in a nonconductive coating applied over an electrically conductive substrate. ASTM D5162 provides procedures for discontinuity testing on metallic substrates. Depending on coating thickness and system requirements, testing may use low-voltage wet-sponge equipment or high-voltage spark testing.

  • Confirm that the coating has cured sufficiently for testing.
  • Verify that the coating and substrate are suitable for the selected method.
  • Use the voltage or test settings required by the specification and coating manufacturer.
  • Establish a reliable electrical ground or return connection.
  • Verify instrument operation before, during, and after testing.
  • Move the electrode at a controlled rate while maintaining proper contact.
  • Mark each discontinuity without damaging or contaminating the lining.
  • Repair and retest every identified holiday.

Excessive Test Voltage Can Damage the Coating

A high-voltage holiday detector is not simply turned up until a spark appears. Excessive voltage can puncture or carbonize an otherwise sound coating, create new defects, damage thin films, and expose personnel to unnecessary electrical hazards.

Test voltage must be established from the approved standard, actual coating thickness, manufacturer instructions, and project specification. Operators must be trained in the equipment and the hazards of its use.

Holiday Detection on Concrete

Holiday testing over concrete can be more difficult because concrete conductivity varies with moisture content, density, thickness, temperature, and contact with ground or reinforcing steel. Dry concrete may not provide a reliable electrical return path.

Some projects use conductive primers, conductive underlayers, grounded metal mesh, or other manufacturer-approved systems to make electrical discontinuity testing possible. These components must be included in the original system design; they should not be improvised after application.

Before testing the entire structure, confirm that the proposed method can reliably detect a known discontinuity in a representative area without damaging the lining.

Adhesion Testing

Pull-off adhesion testing applies a perpendicular tensile force through a bonded loading fixture. ASTM D4541 addresses pull-off testing of coatings on metal substrates. ASTM D7234 addresses pull-off strength of coatings on concrete.

Adhesion testing is normally destructive. Test locations, frequency, loading-fixture size, adhesive, cutting procedure, cure time, test equipment, loading rate, acceptance value, and repair method should be specified before testing begins.

Record both the measured value and the failure location:

  • Adhesive failure between the coating and substrate.
  • Adhesive failure between individual coating layers.
  • Cohesive failure within a coating layer.
  • Cohesive failure within the concrete substrate or repair material.
  • Glue failure between the test fixture and coating.

A numerical value without the failure mode can be misleading. Concrete may fail internally before the bond between the coating and concrete is fully challenged.

Cure and Hardness Verification

A coating may appear dry at the surface before it has developed the cure required for immersion, chemical exposure, disinfection, mechanical service, adhesion testing, or holiday detection.

Cure may be evaluated using one or more approved methods:

  • Elapsed time at documented air and substrate temperatures.
  • Manufacturer-approved hardness testing.
  • Solvent-rub or chemical-resistance testing when appropriate for the chemistry.
  • Shore hardness testing for elastomeric or thick-film systems.
  • Test coupons or retained cure samples produced during application.
  • Product-specific analytical testing when required.

The test method must be appropriate for the coating chemistry. A field method used for one epoxy, polyurethane, polyurea, or vinyl ester system should not automatically be applied to another product.

Repair and Retesting

Defects must be evaluated before repair. The repair procedure should address the cause—not merely cover the visible symptom.

  1. Define and mark the complete defective area.
  2. Determine whether the problem is isolated or evidence of a broader condition.
  3. Remove unsound, contaminated, uncured, or poorly bonded material.
  4. Feather, abrade, clean, and prepare the repair boundary as required.
  5. Apply compatible repair materials within the permitted recoat conditions.
  6. Allow the repair to cure for the specified period.
  7. Repeat the visual, thickness, holiday, adhesion, cure, or other test that identified the defect.
  8. Document the location, cause, procedure, materials, personnel, and retest results.

Repairs should be blended into the surrounding coating without creating abrupt edges, unsealed seams, entrapped contamination, or unverified overlap.

Safety During Inspection and Testing

Inspection inside tanks, wet wells, digesters, vessels, pipelines, and enclosed treatment structures may involve permit-required confined-space hazards. Coating cure does not eliminate atmospheric, engulfment, electrical, access, or process hazards.

Inspectors and testing personnel must be included in the entry permit, atmospheric monitoring, ventilation, communication, lockout, fall-protection, rescue, and personal-protective-equipment plans. Holiday detectors and other electrical instruments must be evaluated for safe use in the work environment.

Required Quality-Control Documentation

The final project record should allow another qualified person to understand what was installed, where it was installed, and how compliance was verified. Records may include:

  • Approved product data sheets, safety data sheets, submittals, and specification sections.
  • Material-delivery records, lot numbers, batch numbers, quantities, and shelf-life verification.
  • Surface-preparation and substrate-condition reports.
  • Environmental readings and ventilation records.
  • Mixing, thinning, induction, pot-life, and plural-component ratio records.
  • Daily production areas, crew assignments, and application times.
  • Wet-film and dry-film thickness readings.
  • Holiday-detection settings, locations, results, repairs, and retests.
  • Adhesion, hardness, cure, and other test results.
  • Nonconformance reports, written dispositions, and corrective actions.
  • Photographs linked to identifiable locations and dates.
  • Final punch-list completion and written acceptance.

Contractor's Field Standard

Inspect each stage before the next stage hides it. Use the correct instrument, follow the specified procedure, record the actual results, correct deficiencies, and retest repairs. A coating system is not complete merely because the final coat has been applied—it is complete when the installed system has been verified and accepted.

Knowledge Check

  1. Why should inspection requirements be established before coating work begins?
  2. What is the difference between contractor quality control and owner quality assurance?
  3. Why are wet-film measurements valuable to the applicator?
  4. Why can conventional magnetic dry-film gauges not be used directly on concrete?
  5. Why must holiday-test voltage be based on the approved procedure and coating thickness?
  6. Why must a pull-off adhesion report include the location and type of failure?
  7. What information should be recorded when a coating defect is repaired?

Technical References

  • AMPP/SSPC-PA 2-2022: Procedure for Determining Conformance to Dry Coating Thickness Requirements.
  • ASTM D7091: Standard Practice for Nondestructive Measurement of Dry Film Thickness of Nonmagnetic Coatings Applied to Ferrous Metals and Nonmagnetic, Nonconductive Coatings Applied to Non-Ferrous Metals.
  • ASTM D4414: Standard Practice for Measurement of Wet Film Thickness by Notch Gages.
  • ASTM D5162-24: Standard Practice for Discontinuity Testing of Nonconductive Protective Coating on Metallic Substrates.
  • ASTM D4541-22: Standard Test Method for Pull-Off Strength of Coatings Using Portable Adhesion Testers on metal substrates.
  • ASTM D7234-22: Standard Test Method for Pull-Off Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers.
  • ASTM D3276: Standard Guide for Painting Inspectors on metal substrates.
  • ASTM D6132: Standard Test Method for Nondestructive Measurement of Dry Film Thickness of Applied Organic Coatings Using an Ultrasonic Coating Thickness Gage.
  • OSHA 29 CFR 1910.146: Permit-Required Confined Spaces.
  • Manufacturer requirements: Current product data sheets, application instructions, inspection procedures, cure requirements, and equipment manuals for the installed system.

Standards may be revised, withdrawn, or replaced. Confirm the current edition required by the contract and obtain the complete standard before developing project procedures. A standard's title or summary is not a substitute for its full requirements.

Professional responsibility: Inspection results must be reported accurately and without selective omission. Do not change acceptance limits, testing frequency, instrument settings, or repair requirements without written authorization from the responsible project authority.

Copyright © 2026 Azimuth Spray Systems, LLC. All Rights Reserved.

No part of this material may be reproduced, copied, distributed, republished, transmitted, stored, or used in any form or by any means without prior written permission from Azimuth Spray Systems, LLC, except for brief quotations used with proper attribution.

AirSprayTech.com - The Finishing Authority®



Was this article helpful?

Comments:
 

Related Articles
 > Academy Series | Professional Certificate Programs
 > Airless Spraying - From Pump to Pattern
 > Airless Spraying—From Pump to Pattern | Article 01 of 18 How Airless Spray Equipment Works
 > Airless Spraying—From Pump to Pattern | Article 02 of 18 How to Read an Airless Spray Tip Number
 > Airless Spraying—From Pump to Pattern | Article 03 of 18 How to Choose the Correct Airless Tip Size
 > Airless Spraying—From Pump to Pattern | Article 04 of 18 Understanding Airless Fan Width and Orifice Size
 > Airless Spraying—From Pump to Pattern | Article 05 of 18 The Right Way to Set Airless Spray Pressure
 > Airless Spraying—From Pump to Pattern | Article 06 of 18 The Perfect Airless Spray Pattern
 > Airless Spraying—From Pump to Pattern | Article 07 of 18 Why an Airless Spray Pattern Develops Tails
 > Airless Spraying—From Pump to Pattern | Article 08 of 18 How Tip Wear Wastes Paint and Changes the Pattern
 > Airless Spraying—From Pump to Pattern | Article 09 of 18 Matching the Tip to the Sprayer’s Capacity
 > Airless Spraying—From Pump to Pattern | Article 10 of 18 How Airless Hose Size and Length Affect Performance
 > Airless Spraying—From Pump to Pattern | Article 11 of 18 How to Prime and Start an Airless Sprayer
 > Airless Spraying—From Pump to Pattern | Article 12 of 18 Professional Airless Spray-Gun Technique
 > Airless Spraying—From Pump to Pattern | Article 13 of 18 How to Shut Down, Flush, and Store an Airless Sprayer
 > Airless Spraying—From Pump to Pattern | Article 14 of 18 Airless Troubleshooting: When the Pump Will Not Prime
 > Airless Spraying—From Pump to Pattern | Article 15 of 18 Airless Troubleshooting: Surging, Pulsing, and Pressure Loss
 > Airless Spraying—From Pump to Pattern | Article 16 of 18 Electric, Gas, or Pneumatic Airless Equipment
 > Airless Spraying—From Pump to Pattern | Article 17 of 18 Choosing the Right Airless Sprayer for the Work
 > Airless Spraying—From Pump to Pattern | Article 18 of 18 Airless Safety: Understanding Injection-Injury Hazards
 > Airless Spraying-From Pump to Pattern Certificate of Completion
 > Airless Spraying—From Pump to Pattern | Final Assessment
 > Powder Coating - From Particle To Performance
 > Powder Coating—From Particle to Performance | Article 01 of 32 | The History of Powder Coating
 > Powder Coating—From Particle to Performance | Article 02 of 32 | What Powder Coating Is—and What It Is Not
 > Powder Coating—From Particle to Performance | Article 03 of 32 | What Is Inside a Powder Coating?
 > Powder Coating—From Particle to Performance | Article 04 of 32 | How Powder Coating Is Manufactured
 > Powder Coating—From Particle to Performance | Article 05 of 32 | Thermoset Versus Thermoplastic Powder Coatings
 > Powder Coating—From Particle to Performance | Article 06 of 32 | Epoxy, Polyester, and Epoxy-Polyester Hybrid Powders
 > Powder Coating—From Particle to Performance | Article 07 of 32 | Polyurethane, Acrylic, Fluoropolymer, and Specialty Powders
 > Powder Coating—From Particle to Performance | Article 08 of 32 | Selecting the Right Powder for the Application
 > Powder Coating—From Particle to Performance | Article 09 of 32 | Why Surface Preparation Determines Coating Performance
 > Powder Coating—From Particle to Performance | Article 10 of 32 | Preparing Steel, Aluminum, and Galvanized Surfaces
 > Powder Coating—From Particle to Performance | Article 11 of 32 | Mechanical Surface Preparation for Powder Coating
 > Powder Coating—From Particle to Performance | Article 12 of 32 | Chemical Pretreatment, Rinsing, and Dry-Off
 > Powder Coating—From Particle to Performance | Article 13 of 32 | How Electrostatic Powder Coating Works
 > Powder Coating—From Particle to Performance | Article 14 of 32 | Corona-Charging Powder Guns
 > Powder Coating—From Particle to Performance | Article 15 of 32 | Tribostatic Powder Application
 > Powder Coating—From Particle to Performance | Article 16 of 32 | Fluidized-Bed Powder Coating
 > Powder Coating—From Particle to Performance | Article 17 of 32: Anatomy of a Manual Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 18 of 32: Anatomy of an Automatic Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 19 of 32: Powder Booths, Airflow, and Containment
 > Powder Coating—From Particle to Performance | Article 20 of 32: Powder Feed, Recovery, Reclaim, and Color Change
 > Powder Coating—From Particle to Performance | Article 21 of 32: Compressed-Air Quality for Powder-Coating Equipment
 > Powder Coating—From Particle to Performance | Article 22 of 32: How to Set Up and Start a Powder-Coating System
 > Powder Coating—From Particle to Performance | Article 23 of 32: Setting Powder Flow, Pattern Air, kV, and Current
 > Powder Coating—From Particle to Performance | Article 24 of 32: Professional Manual Powder-Gun Technique
 > Powder Coating—From Particle to Performance | Article 25 of 32: Setting Up Automatic Guns and Reciprocators
 > Powder Coating—From Particle to Performance | Article 26 of 32: Faraday-Cage Effect, Back Ionization, and Poor Coverage
 > Powder Coating—From Particle to Performance | Article 27 of 32: Curing Powder Coating—Time at Metal Temperature
 > Powder Coating—From Particle to Performance | Article 28 of 32: Oven Profiling and Cure Verification
 > Powder Coating—From Particle to Performance | Article 29 of 32: Measuring Powder-Coating Film Thickness
 > Powder Coating—From Particle to Performance | Article 30 of 32: Testing Adhesion, Cure, Gloss, Color, and Appearance
 > Powder Coating—From Particle to Performance | Article 31 of 32: Powder-Coating Defects and Corrective Action
 > Powder Coating—From Particle to Performance | Article 32 of 32: Powder-Coating Safety, Housekeeping, and Preventive Maintenance
 > Powder Coating—From Particle to Performance | Final Course Assessment
 > Powder Coating—From Particle to Performance | Certificate of Completion
 > Powder Coating—From Particle to Performance | Request a Certificate of Completion
 > Finishing Quality - From Spec to Sign-Off | AirSprayTech Academy
 > Finishing Quality—From Spec to Sign-Off | Article 01 of 28: Quality Begins with the Specification
 > Finishing Quality—From Spec to Sign-Off | Article 02 of 28: From Specification to Control Plan
 > Finishing Quality—From Spec to Sign-Off | Article 03 of 28: Document Control and Traceability
 > Finishing Quality—From Spec to Sign-Off | Article 04 of 28: Incoming Materials and Receiving Inspection
 > Finishing Quality—From Spec to Sign-Off | Article 05 of 28: Incoming Process Water Quality
 > Finishing Quality—From Spec to Sign-Off | Article 06 of 28: Process Water Treatment Systems
 > Finishing Quality—From Spec to Sign-Off | Article 07 of 28 Treating and Releasing Finishing Wastewater
 > Finishing Quality—From Spec to Sign-Off | Article 08 of 28: Surface Cleaning and Contamination Control
 > Finishing Quality—From Spec to Sign-Off | Article 09 of 28 Surface Pretreatment and Conversion Coating Control
 > Finishing Quality—From Spec to Sign-Off | Article 10 of 28 Coating Material Storage, Mixing, and Conditioning
 > Finishing Quality—From Spec to Sign-Off | Article 11 of 28 Compressed-Air Quality and System Control
 > Finishing Quality—From Spec to Sign-Off | Article 12 of 28 Temperature, Humidity, and Environmental Control
 > Finishing Quality—From Spec to Sign-Off | Article 13 of 28 Application Equipment Setup and Process Verification
 > Finishing Quality—From Spec to Sign-Off | Article 14 of 28 Wet-Film Thickness and Application Control
 > Finishing Quality—From Spec to Sign-Off | Article 15 of 28 Dry-Film Thickness Measurement and Control
 > Finishing Quality—From Spec to Sign-Off | Article 16 of 28 Cure Verification and Oven Performance
 > Finishing Quality—From Spec to Sign-Off | Article 17 of 28 Appearance, Color, Gloss, and Texture Inspection
 > Finishing Quality—From Spec to Sign-Off | Article 18 of 28 Coating Adhesion Testing and Interpretation
 > Finishing Quality—From Spec to Sign-Off | Article 19 of 28 Hardness, Impact, Flexibility, and Abrasion Testing
 > Finishing Quality—From Spec to Sign-Off | Article 20 of 28 Corrosion, Chemical, and Environmental Exposure Testing
 > Finishing Quality—From Spec to Sign-Off | Article 21 of 28 Holiday, Porosity, and Coating-Continuity Testing
 > Finishing Quality—From Spec to Sign-Off | Article 22 of 28 Building and Controlling the In-House Finishing Laboratory
 > Finishing Quality—From Spec to Sign-Off | Article 23 of 28 Sampling Plans and Inspection Frequency
 > Finishing Quality—From Spec to Sign-Off | Article 24 of 28 Building the Finishing Process Data Highway
 > Finishing Quality—From Spec to Sign-Off | Article 25 of 28 Nonconformance, Root Cause, and Corrective Action
 > Finishing Quality—From Spec to Sign-Off | Article 26 of 28 Final Product Audit, Acceptance, and Release
 > Finishing Quality—From Spec to Sign-Off | Article 27 of 28 Build a Quality Team That Includes the People Doing the Work
 > Finishing Quality—From Spec to Sign-Off | Article 28 of 28 Your Vendors Are Part of the Quality Team
 > Finishing Quality—From Spec to Sign-Off | Final Assessment
 > Finishing Quality—From Spec to Sign-Off | Certificate Request
 > Paint Shop Planning - From Floor Plan to First Spray
 > Paint Shop Planning—From Floor Plan to First Spray | Article 02 of 28 | Build a Project Team Before You Build the Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 03 of 28 | Meet the Authority Having Jurisdiction Early
 > Paint Shop Planning—From Floor Plan to First Spray | Article 04 of 28 | Creating the Owner’s Project Requirements
 > Paint Shop Planning—From Floor Plan to First Spray | Article 05 of 28 | Understanding NFPA 33 and Spray-Application Fire Protection
 > Paint Shop Planning—From Floor Plan to First Spray | Article 06 of 28 | Understanding the NEC in a Paint Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 07 of 28 | Flammable and Combustible Liquid Storage
 > Paint Shop Planning—From Floor Plan to First Spray | Article 08 of 28 | Building, Fire, and Mechanical Codes
 > Paint Shop Planning—From Floor Plan to First Spray | Article 09 of 28 | Environmental Permits and Emissions Planning
 > Paint Shop Planning—From Floor Plan to First Spray | Article 10 of 28 | Planning the Shop Layout and Product Flow
 > Paint Shop Planning—From Floor Plan to First Spray | Article 11 of 28 | Spray-Booth and Preparation-Station Selection
 > Paint Shop Planning—From Floor Plan to First Spray | Article 12 of 28 | Air-Makeup and Exhaust-System Planning
 > Paint Shop Planning—From Floor Plan to First Spray | Article 13 of 28 | Planning the Compressed-Air System
 > Paint Shop Planning—From Floor Plan to First Spray | Article 14 of 28 | Electrical Service, Controls, and Hazardous Locations
 > Paint Shop Planning—From Floor Plan to First Spray | Article 15 of 28 | Natural Gas, Heating, and Curing Requirements
 > Paint Shop Planning—From Floor Plan to First Spray | Article 16 of 28 | Fire Suppression, Detection, and Emergency Systems
 > Paint Shop Planning—From Floor Plan to First Spray | Article 17 of 28 | Writing an Equipment Specification Vendors Can Quote
 > Paint Shop Planning—From Floor Plan to First Spray | Article 18 of 28 | How to Compare Paint-Booth Proposals
 > Paint Shop Planning—From Floor Plan to First Spray | Article 19 of 28 | Who Is Responsible for What?
 > Paint Shop Planning—From Floor Plan to First Spray | Article 20 of 28 | Site Preparation and Construction Coordination
 > Paint Shop Planning—From Floor Plan to First Spray | Article 21 of 28 | Change Orders: Where Paint-Shop Budgets Go to Die
 > Paint Shop Planning—From Floor Plan to First Spray | Article 22 of 28 | Pre-Startup Inspection and Documentation
 > Paint Shop Planning—From Floor Plan to First Spray | Article 23 of 28 | Testing Booth Airflow and Pressure
 > Paint Shop Planning—From Floor Plan to First Spray | Article 24 of 28 | Testing Safety Interlocks and Emergency Controls
 > Paint Shop Planning—From Floor Plan to First Spray | Article 25 of 28 | Commissioning the Complete Paint Shop
 > Paint Shop Planning—From Floor Plan to First Spray | Article 26 of 28 | Training Operators and Maintenance Personnel
 > Paint Shop Planning—From Floor Plan to First Spray | Article 27 of 28 | Final Acceptance: Do Not Sign Off Until It Performs
 > Paint Shop Planning—From Floor Plan to First Spray | Article 28 of 28 | Planning for Maintenance, Expansion, and the Next Ten Years
 > Paint Shop Planning—From Floor Plan to First Spray | Article 01 of 28 | Before You Buy a Booth: Define the Finishing Process
 > Paint Shop Planning—From Floor Plan to First Spray | Final Assessment
 > Paint Shop Planning—From Floor Plan to First Spray | Certificate of Completion Request
 > Automotive Refinish - From Repair Plan to Road Ready
 > Automotive Refinish—From Repair Plan to Road Ready | Article 01 of 28 | Start Before the Sandpaper: Vehicle Intake and Refinish Planning
 > Automotive Refinish—From Repair Plan to Road Ready | Article 02 of 28 | PPE Is Part of the Process: Protecting the Automotive Painter
 > Automotive Refinish—From Repair Plan to Road Ready | Article 03 of 28 | Fire, Fumes, and Ignition Sources: Everyday Refinish-Shop Safety
 > Automotive Refinish—From Repair Plan to Road Ready | Article 04 of 28 | A Clean Shop Paints Cleaner Cars: Housekeeping and Contamination Control
 > Automotive Refinish—From Repair Plan to Road Ready | Article 05 of 28 | Know What You Are Painting: Automotive Substrate Identification
 > Automotive Refinish—From Repair Plan to Road Ready | Article 06 of 28 | Clean Before You Cut: Washing, Degreasing, and Contamination Removal
 > Automotive Refinish—From Repair Plan to Road Ready | Article 07 of 28 | Stop Corrosion Before It Starts: Bare Metal and Corrosion Protection
 > Automotive Refinish—From Repair Plan to Road Ready | Article 08 of 28 | Sand With a Purpose: Abrasives, Grit Selection, and Surface Profiles
 > Automotive Refinish—From Repair Plan to Road Ready | Article 09 of 28 | Build It Straight: Fillers, Glazes, Primers, and Sealers
 > Automotive Refinish—From Repair Plan to Road Ready | Article 10 of 28 | Mask the Repair, Not the Mistake: Paper, Plastic, Tape, and Technique
 > Automotive Refinish—From Repair Plan to Road Ready | Article 11 of 28 | Choose the Complete System: Modern Automotive-Refinish Materials
 > Automotive Refinish—From Repair Plan to Road Ready | Article 12 of 28 | Control the Mix: Paint Storage, Mixing Rooms, and Material Management
 > Automotive Refinish—From Repair Plan to Road Ready | Article 13 of 28 | Match It Before You Spray It: Color Tools, Spray-Outs, and Color Acceptance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 14 of 28 | Choose the Right Spray Gun: Match the Equipment to the Finish
 > Automotive Refinish—From Repair Plan to Road Ready | Article 15 of 28 | Feed the Finish: Air-Compressor Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 16 of 28 | Keep the Gun Honest: Spray Equipment Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 17 of 28 | Paint With a Plan: Professional Basecoat and Clearcoat Application
 > Automotive Refinish—From Repair Plan to Road Ready | Article 18 of 28 | Control the Booth: Airflow, Filters, Lighting, and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 19 of 28 | Balance the Booth: Air-Makeup Unit Operation and Maintenance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 20 of 28 | Cure It by the Numbers: Flash, Bake, and Return-to-Service
 > Automotive Refinish—From Repair Plan to Road Ready | Article 21 of 28 | Correct Without Creating: Denibbing, Sanding, and Polishing
 > Automotive Refinish—From Repair Plan to Road Ready | Article 22 of 28 | Put It Back Right: Reassembly Without Damaging the Finish
 > Automotive Refinish—From Repair Plan to Road Ready | Article 23 of 28 | Inspect It Before the Customer Does: Final Quality Control
 > Automotive Refinish—From Repair Plan to Road Ready | Article 24 of 28 | Deliver More Than Shine: Customer Handoff and Fresh-Paint Care
 > Automotive Refinish—From Repair Plan to Road Ready | Article 25 of 28 | Control the Waste Stream: Paint, Solvent, Filters, and Compliance
 > Automotive Refinish—From Repair Plan to Road Ready | Article 26 of 28 | Troubleshoot the Process: Find the Cause Before Repainting
 > Automotive Refinish—From Repair Plan to Road Ready | Article 27 of 28 | Make Quality Repeatable: Procedures, Training, and Team Accountability
 > Automotive Refinish—From Repair Plan to Road Ready | Article 28 of 28 | Road Ready Is Earned: Audit the Complete Refinish Process
 > Automotive Refinish—From Repair Plan to Road Ready | Final Assessment
 > Automotive Refinish—From Repair Plan to Road Ready | Certificate of Completion Request
 > Corrosion Protection for Industrial Coating Contractors - 00 Course Overview
 > Corrosion Protection for Industrial Coating Contractors - Article 01: Understanding Corrosion
 > Corrosion Protection for Industrial Coating Contractors - Article 02: Common Forms of Corrosion
 > Corrosion Protection for Industrial Coating Contractors - Article 03: Evaluating the Structure and Service Environment
 > Corrosion Protection for Industrial Coating Contractors - Article 04: Protective Coatings as the Primary Barrier
 > Corrosion Protection for Industrial Coating Contractors - Article 05: Selecting the Correct Coating System
 > Corrosion Protection for Industrial Coating Contractors - Article 06: Surface Cleanliness and Contaminant Testing
 > Corrosion Protection for Industrial Coating Contractors - Article 07: Abrasive Blasting and Surface-Preparation Standards
 > Corrosion Protection for Industrial Coating Contractors - Article 08: Surface Profile and Anchor Pattern
 > Corrosion Protection for Industrial Coating Contractors - Article 09: Environmental Conditions and Dew Point Control
 > Corrosion Protection for Industrial Coating Contractors - Article 10: Selecting Coating Systems for the Service Environment
 > Corrosion Protection for Industrial Coating Contractors - Article 11: Primers and Their Role in Corrosion Protection
 > Corrosion Protection for Industrial Coating Contractors - Article 12: Intermediate Coats, Finish Coats, and Stripe Coating
 > Corrosion Protection for Industrial Coating Contractors - Article 13: Coating Application Methods and Spray Technique
 > Corrosion Protection for Industrial Coating Contractors - Article 14: Coating Mixing, Thinning, Induction Time, and Pot Life
 > Corrosion Protection for Industrial Coating Contractors - Article 15: Wet Film and Dry Film Thickness Control
 > Corrosion Protection for Industrial Coating Contractors - Article 16: Holidays, Pinholes, and Discontinuity Testing
 > Corrosion Protection for Industrial Coating Contractors - Article 17: Coating Adhesion Testing and Failure Interpretation
 > Corrosion Protection for Industrial Coating Contractors - Article 18: Coating Defects and Failure Diagnosis
 > Corrosion Protection for Industrial Coating Contractors - Article 19: How Coatings and Cathodic Protection Work Together
 > Corrosion Protection for Industrial Coating Contractors - Article 20: Final Inspection, Repair Verification, and Project Documentation
 > Corrosion Protection for Industrial Coating Contractors - Final Assessment
 > Corrosion Protection for Industrial Coating Contractors - Final Certificate of Completion Request
 > Protective Linings for Industrial Coating Contractors | 00 - Course Overview
 > Protective Linings for Industrial Coating Contractors | Article 01 of 20 - Protective Linings: What They Are and Why They Fail
 > Protective Linings for Industrial Coating Contractors | Article 02 of 20 - Understanding the Lining Service Environment
 > Protective Linings for Industrial Coating Contractors | Article 04 of 20 - Selecting a Lining for the Material Being Contained
 > Protective Linings for Industrial Coating Contractors | Article 05 of 20 - Epoxy Linings and Where They Are Used
 > Protective Linings for Industrial Coating Contractors | Article 06 of 20 - Novolac Epoxy Linings for Severe Chemical Service
 > Protective Linings for Industrial Coating Contractors | Article 07 of 20 - Vinyl Ester and Polyester Lining Systems
 > Protective Linings for Industrial Coating Contractors | Article 08 of 20 - Polyurethane, Polyurea, and Elastomeric Linings
 > Protective Linings for Industrial Coating Contractors | Article 09 of 20 - Cementitious and Specialty Lining Systems
 > Protective Linings for Industrial Coating Contractors | Article 10 of 20 - Inspecting Steel and Concrete Before Lining Work Begins
 > Protective Linings for Industrial Coating Contractors | Article 11 of 20 - Preparing Steel for Protective-Lining Application
 > Protective Linings for Industrial Coating Contractors | Article 12 of 20 - Preparing Concrete for Protective Linings
 > Protective Linings for Industrial Coating Contractors | Article 13 of 20 - Moisture in Concrete: When a Lining Should Not Be Applied
 > Protective Linings for Industrial Coating Contractors | Article 14 of 20 - Environmental Conditions, Dew Point, and Condensation Control
 > Protective Linings for Industrial Coating Contractors | Article 15 of 20 - Mixing, Induction Time, Pot Life, and Material Temperature
 > Protective Linings for Industrial Coating Contractors | Article 16 of 20 - Applying High-Build and Plural-Component Linings
 > Protective Linings for Industrial Coating Contractors | Article 17 of 20 - Stripe Coating, Edges, Welds, Penetrations, and Difficult Areas
 > Protective Linings for Industrial Coating Contractors | Article 18 of 20 - Film Thickness, Recoat Windows, Curing, and Return to Service
 > Protective Linings for Industrial Coating Contractors | Article 19 of 20 - Inspecting Protective Linings
 > Protective Linings for Industrial Coating Contractors | Article 20 of 20 - Final Acceptance, Repairs, and Lining Maintenance
 > Protective Linings for Industrial Coating Contractors - Final Assessment
 > Protective Linings for Industrial Coating Contractors | Certificate of Completion Request
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | 00 - Course Overview
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 01 of 20 - Why Moisture Causes Coating and Flooring Fail
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 03 of 20 - Moisture Vapor Versus Hydrostatic Pressure
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 02 of 20 - How Moisture Moves Through Concrete
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 04 of 20 - Sources of Moisture in Concrete Slabs and Str
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 05 of 20 - Recognizing Moisture-Related Coating Failures
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 06 of 20 - Relative-Humidity Testing of Concrete Slabs
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 07 of 20 - Calcium-Chloride Moisture-Vapor-Emission Test
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 08 of 20 - Electronic Moisture Meters and Surface-Moistu
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 09 of 20 - Concrete pH and Alkalinity at the Bond Line
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 10 of 20 - Dew Point, Condensation, and Environmental Co
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 11 of 20 - Osmotic Blistering, Delamination, and Efflore
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 12 of 20 - When a Coating Should Not Be Applied
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 13 of 20 - Selecting a Moisture-Mitigation System
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 14 of 20 - Surface Preparation for Moisture-Mitigation M
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 15 of 20 - Applying Moisture-Mitigation Membranes
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 16 of 20 - Pinholes, Holidays, and Membrane Inspection
 > Moisture Vapor Barriers and Mitigation Membranes for Industrial Coating Contractors | Article 17 of 20 - Primers, Underlayments, Adhesives, and System
 > Moisture Vapor Management | 18 - Repairing Coating and Flooring Failures
 > Moisture Vapor Management | 19 - Documentation, Warranties, and Contractor Liability
 > Moisture Vapor Management | 20 - Complete Moisture-Management Plan
 > Moisture Vapor Management | Course Assessment
 > Moisture Vapor Management | Certificate Request
 > Commercial and Industrial Floor Coatings - Course Overview
 > Commercial and Industrial Floor Coatings | Article 01 of 24 | What Floor Coatings Must Do
 > Commercial and Industrial Floor Coatings | Article 02 of 24 | Defining the Service Environment
 > Commercial and Industrial Floor Coatings | Article 03 of 24 | Evaluating Existing Concrete and Previous Floors
 > Commercial and Industrial Floor Coatings | Article 04 of 24 | Concrete Moisture and Floor-Coating Failure
 > Commercial and Industrial Floor Coatings | Article 05 of 24 | Removing Oil, Grease and Chemical Contamination
 > Commercial and Industrial Floor Coatings | Article 06 of 24 | Mechanical Surface Preparation
 > Commercial and Industrial Floor Coatings | Article 07 of 24 | Concrete Surface Profile and Preparation Acceptance
 > Commercial and Industrial Floor Coatings | Article 08 of 24 | Repairing Cracks, Joints, Spalls and Damaged Concrete
 > Commercial and Industrial Floor Coatings | Article 09 of 24 | Primers, Patches, Underlayments and Moisture Mitigation
 > Commercial and Industrial Floor Coatings | Article 10 of 24 | Understanding Resinous Floor-Coating Chemistries
 > Commercial and Industrial Floor Coatings | Article 11 of 24 | Epoxy Floor-Coating Systems
 > Commercial and Industrial Floor Coatings | Article 12 of 24 | Polyurethane and Polyaspartic Floor Coatings
 > Commercial and Industrial Floor Coatings | Article 13 of 24 | Urethane-Cement Flooring for Heavy-Duty and Sanitary Service
 > Commercial and Industrial Floor Coatings | Article 14 of 24 | Methyl Methacrylate and Rapid-Return Flooring Systems
 > Commercial and Industrial Floor Coatings | Article 15 of 24 | Broadcast, Slurry, Mortar, and Self-Leveling Floor Systems
 > Commercial and Industrial Floor Coatings | Article 16 of 24 | Slip Resistance, Texture, Cleanability, and Appearance
 > Commercial and Industrial Floor Coatings | Article 17 of 24 | Coves, Drains, Penetrations, Edges, and Floor Transitions
 > Commercial and Industrial Floor Coatings | Article 18 of 24 | Mixing, Staging, Pot Life, and Installation Sequence
 > Commercial and Industrial Floor Coatings | Article 19 of 24 | Coverage, Film Thickness, Aggregate, and Material Control
 > Commercial and Industrial Floor Coatings | Article 20 of 24 | Environmental Conditions, Cure, Recoat Windows, and Return to Service
 > Commercial and Industrial Floor Coatings | Article 21 of 24 | Warehouse, Manufacturing, Vehicle and Aircraft-Hangar Floors
 > Commercial and Industrial Floor Coatings | Article 22 of 24 | Food, Beverage, Sanitary, Healthcare and Cleanroom Floors
 > Commercial and Industrial Floor Coatings | Article 23 of 24 | Inspection, Testing, Defects and Repairs
 > Commercial and Industrial Floor Coatings | Article 24 of 24 | Estimating, Documentation, Warranties, Maintenance and Final Acceptance
 > Commercial and Industrial Floor Coatings | Final Course Assessment
 > Commercial and Industrial Floor Coatings | Certificate of Completion Request
 > Commercial and Industrial Roof Coatings | 00 Certificate Program
 > Commercial and Industrial Roof Coatings | 01 of 25: What They Must Dand
 > Commercial and Industrial Roof Coatings | 02 of 25 | Coatings vs. Membranes
 > Commercial and Industrial Roof Coatings | 03 of 25 | Roof Assemblies and Substrates
 > Commercial and Industrial Roof Coatings | 04 of 25 | Reading the Specification
 > Commercial and Industrial Roof Coatings | 05 of 25 | Codes, Fire, Wind, and Energy
 > Commercial and Industrial Roof Coatings | 06 of 25 | New-Construction Readiness
 > Commercial and Industrial Roof Coatings | 07 of 25 | Restore or Replace
 > Commercial and Industrial Roof Coatings | 08 of 25 | Roof Moisture Surveys
 > Commercial and Industrial Roof Coatings | 09 of 25 | Drainage and Ponding Water
 > Commercial and Industrial Roof Coatings | 10 of 25 | Repairs Before Coating
 > Commercial and Industrial Roof Coatings | 11 of 25 | Cleaning and Contamination Removal
 > Commercial and Industrial Roof Coatings | 12 of 25 | Surface Preparation by Substrate
 > Commercial and Industrial Roof Coatings | 13 of 25 | Adhesion Testing
 > Commercial and Industrial Roof Coatings | 14 of 25 | Primers and Tie Coats
 > Commercial and Industrial Roof Coatings | 15 of 25 | Elastomeric Coatings
 > Commercial and Industrial Roof Coatings | 16 of 25 | Acrylic Systems
 > Commercial and Industrial Roof Coatings | 17 of 25 | Silicone Systems
 > Commercial and Industrial Roof Coatings | 18 of 25 | Polyurethane Systems
 > Commercial and Industrial Roof Coatings | 19 of 25 | PMMA Membranes
 > Commercial and Industrial Roof Coatings | 20 of 25 | Polyurea Membranes
 > Commercial and Industrial Roof Coatings | 21 of 25 | Spray Equipment
 > Commercial and Industrial Roof Coatings | 22 of 25 | Weather and Cure
 > Commercial and Industrial Roof Coatings | 23 of 25 | Inspection and Repairs
 > Commercial and Industrial Roof Coatings | 24 of 25 | Specifications and Warranties
 > Commercial and Industrial Roof Coatings | 25 of 25 | Technical Glossary
 > Commercial and Industrial Roof Coatings | Course Assessment
 > Commercial and Industrial Roof Coatings | Certificate Request
 > Professional Line Striping for Contractors | Course Overview
 > Professional Line Striping for Contractors | Article 01 of 24 | The Contractor’s Role
 > Professional Line Striping for Contractors | Article 02 of 24 | Plans, Specifications and Scope
 > Professional Line Striping for Contractors | Article 03 of 24 | Site Survey and Prejob Evaluation
 > Professional Line Striping for Contractors | Article 04 of 24 | MUTCD Marking Fundamentals
 > Professional Line Striping for Contractors | Article 05 of 24 | Accessible Parking Spaces
 > Professional Line Striping for Contractors | Article 06 of 24 | Fire Lanes and Restricted Areas
 > Professional Line Striping for Contractors | Article 07 of 24 | Parking-Lot Layout and Traffic Flow
 > Professional Line Striping for Contractors | Article 08 of 24 | Measuring and Layout Control
 > Professional Line Striping for Contractors | Article 09 of 24 | Pavement and Existing Markings
 > Professional Line Striping for Contractors | Article 10 of 24 | Surface Preparation and Marking Removal
 > Professional Line Striping for Contractors | Article 11 of 24 | Selecting Marking Materials
 > Professional Line Striping for Contractors | Article 12 of 24 | Marking Coating Chemistries
 > Professional Line Striping for Contractors | Article 13 of 24 | Glass Beads and Retroreflectivity
 > Professional Line Striping for Contractors | Article 14 of 24 | Striping Machines, Guns and Tips
 > Professional Line Striping for Contractors | Article 15 of 24 | Equipment Setup and Spray Control
 > Professional Line Striping for Contractors | Article 16 of 24 | Width, Thickness and Coverage
 > Professional Line Striping for Contractors | Article 17 of 24 | Stencils, Symbols and Arrows
 > Professional Line Striping for Contractors | Article 18 of 24 | Weather, Moisture, Drying and Cure
 > Professional Line Striping for Contractors | Article 19 of 24 | Work-Zone Traffic Control
 > Professional Line Striping for Contractors | Article 20 of 24 | Crew Positioning, Communication and PPE
 > Professional Line Striping for Contractors | Article 21 of 24 | Estimating Line Striping Work
 > Professional Line Striping for Contractors | Article 22 of 24 | Scheduling and Managing Crews
 > Professional Line Striping for Contractors | Article 23 of 24 | Inspection, Defects and Acceptance
 > Professional Line Striping for Contractors | Article 24 of 24 | Documentation, Maintenance and Growth
 > Professional Line Striping for Contractors | Course Assessment
 > Professional Line Striping for Contractors | Certificate Request
 > Academy Educational Standards and Editorial Policy
 > Secondary Containment Coating Systems | 00 Course Overview
 > Secondary Containment Coating Systems | Article 01 of 24 | Purpose and Responsibility
 > Secondary Containment Coating Systems | Article 02 of 24 | Defining the Service Environment
 > Secondary Containment Coating Systems | Article 03 of 24 | Chemical Exposure Variables
 > Secondary Containment Coating Systems | Article 04 of 24 | Concrete and Steel Structures
 > Secondary Containment Coating Systems | Article 06 of 24 | Concrete Moisture and Failure
 > Secondary Containment Coating Systems | Article 07 of 24 | Embedded Concrete Contamination
 > Secondary Containment Coating Systems | Article 08 of 24 | Mechanical Concrete Preparation
 > Secondary Containment Coating Systems | Article 09 of 24 | Steel Surface Preparation
 > Secondary Containment Coating Systems | Article 10 of 24 | Primers and Bonding Layers
 > Secondary Containment Coating Systems | Article 12 of 24 | Vinyl Ester Systems
 > Secondary Containment Coating Systems | Article 14 of 24 | Fiberglass-Reinforced Linings
 > Secondary Containment Coating Systems | Article 15 of 24 | Coves, Joints, Drains, and Penetrations
 > Secondary Containment Coating Systems | Article 16 of 24 | Mixing, Staging, and Pot Life
 > Secondary Containment Coating Systems | Article 17 of 24 | Application Methods and Equipment
 > Secondary Containment Coating Systems | Article 18 of 24 | Film Thickness and Continuity
 > Secondary Containment Coating Systems | Article 19 of 24 | Environmental Conditions and Cure
 > Secondary Containment Coating Systems | Article 20 of 24 | Inspection, Testing, and Final Acceptance
 > Secondary Containment Coating Systems | Article 21 of 24 | Defects, Failure Analysis, and Repairs
 > Secondary Containment Coating Systems | Article 22 of 24 | Spill Response and Return to Service
 > Secondary Containment Coating Systems | Article 23 of 24 | Inspection, Maintenance, and Service Life
 > Secondary Containment Coating Systems | Article 24 of 24 | Estimating and Contractor Responsibility
 > Secondary Containment Coating Systems | Course Assessment
 > Secondary Containment Coating Systems | Certificate of Completion Request
 > Portable Plural-Component Coating Systems | 00 Course Overview
 > Portable Plural-Component Systems | Article 01 of 24 | Understanding the System
 > Portable Plural-Component Systems | Article 02 of 24 | Ratios and Stoichiometry
 > Portable Plural-Component Systems | Article 03 of 24 | Pot Life and Cure
 > Portable Plural-Component Systems | Article 04 of 24 | Materials and Applications
 > Portable Plural-Component Systems | Article 05 of 24 | Reading the Documents
 > Portable Plural-Component Systems | Article 06 of 24 | How Proportioners Work
 > Portable Plural-Component Systems | Article 07 of 24 | Selecting a Proportioner
 > Portable Plural-Component Systems | Article 08 of 24 | Pails, Drums, Totes, and Feed Pumps
 > Portable Plural-Component Systems | Article 09 of 24 | Pumps and Ratio Control
 > Portable Plural-Component Systems | Article 10 of 24 | Material Conditioning
 > Portable Plural-Component Systems | Article 11 of 24 | Heating and Temperature Control
 > Portable Plural-Component Systems | Article 12 of 24 | Filters, Valves, Gauges, and Sensors
 > Portable Plural-Component Systems | Article 13 of 24 | Manifolds and Mixers
 > Portable Plural-Component Systems | Article 14 of 24 | Spray Guns, Tips, and Chambers
 > Portable Plural-Component Systems | Article 15 of 24 | Building a Mobile Rig
 > Portable Plural-Component Systems | Article 16 of 24 | Hoses and Connections
 > Portable Plural-Component Systems | Article 17 of 24 | Calibration and Ratio Testing
 > Portable Plural-Component Systems | Article 18 of 24 | Jobsite Setup and Startup
 > Portable Plural-Component Systems | Article 19 of 24 | Pressure and Spray Technique
 > Portable Plural-Component Systems | Article 20 of 24 | Film Thickness and Cure
 > Portable Plural-Component Systems | Article 21 of 24 | Correcting Off-Ratio Material
 > Portable Plural-Component Systems | Article 22 of 24 | Shutdown and Flushing
 > Portable Plural-Component Systems | Article 23 of 24 | Troubleshooting and Maintenance
 > Portable Plural-Component Systems | Article 24 of 24 | Final Acceptance
 > Portable Plural-Component Coating Systems | Course Assessment
 > Portable Plural-Component Systems | Certificate of Completion Request
 > 2K and 3K Coating Systems | 00 Course Overview
 > 2K and 3K Coating Systems | Article 01 of 24: Understanding Production Systems
 > 2K and 3K Coating Systems | Article 02 of 24: Reactive Coating Chemistries
 > 2K and 3K Coating Systems | Article 03 of 24: Components A, B, and C
 > 2K and 3K Coating Systems | Article 04 of 24: Mixing Ratios and Tolerances
 > 2K and 3K Coating Systems | Article 05 of 24: Viscosity and Temperature
 > 2K and 3K Coating Systems | Article 06 of 24: Material Supply Systems
 > 2K and 3K Coating Systems | Article 07 of 24: Metering and Dosing
 > 2K and 3K Coating Systems | Article 08 of 24: Static and Dynamic Mixing
 > 2K and 3K Coating Systems | Article 09 of 24: Pot Life and Mixed Volume
 > 2K and 3K Coating Systems | Article 10 of 24: Flushing and Color Change
 > 2K and 3K Coating Systems | Article 11 of 24: Pressure and Flow Control
 > 2K and 3K Coating Systems | Article 12 of 24: Applicators and Atomization
 > 2K and 3K Coating Systems | Article 13 of 24: Color Change and Multiple-Hardener System Design
 > 2K and 3K Coating Systems | Article 14 of 24: Pot Life and Production Interruptions
 > 2K and 3K Coating Systems | Article 15 of 24: Calibration and Ratio Verification
 > 2K and 3K Coating Systems | Article 16 of 24: Flow, Pressure, Alarms, and Interlocks
 > 2K and 3K Coating Systems | Article 17 of 24: Startup, Production, and Shutdown
 > 2K and 3K Coating Systems | Article 18 of 24: Solvent and Waste Reduction
 > 2K and 3K Coating Systems | Article 19 of 24: Containing Off-Ratio Material
 > 2K and 3K Coating Systems | Article 20 of 24: Troubleshooting Ratio, Flow, Pressure, and Mixing Problems
 > 2K and 3K Coating Systems | Article 21 of 24: Production Operating Procedures
 > 2K and 3K Coating Systems | Article 22 of 24: Worker and Facility Safety
 > 2K and 3K Coating Systems | Article 23 of 24: Quality Control and Traceability
 > 2K and 3K Coating Systems | Article 24 of 24: System Acceptance and Lifecycle Management
 > 2K and 3K Coating Systems for OEM Product Finishers | Course Assessment
 > 2K and 3K Coating Systems | Certificate of Completion Request
 > Water and Wastewater Protective Coating Systems | 00 Course Overview
 > Water & Wastewater Coatings | Article 01 of 24: What Protective Systems Must Do
 > Water & Wastewater Coatings | Article 02 of 24: Mapping the Treatment Process
 > Water & Wastewater Coatings | Article 03 of 24: Defining Exposure Zones
 > Water & Wastewater Coatings | Article 04 of 24: Reading Project Requirements
 > Water & Wastewater Coatings | Article 05 of 24: Potable-Water Certification
 > Water & Wastewater Coatings | Article 06 of 24: Hydrogen Sulfide Corrosion
 > Water & Wastewater Coatings | Article 07 of 24: Evaluating Existing Concrete
 > Water & Wastewater Coatings | Article 08 of 24: Evaluating Existing Steel
 > Water and Wastewater Protective Coating Systems | Article 09 of 24: Cleaning and Decontamination
 > Water and Wastewater Protective Coating Systems | Article 10 of 24: Concrete Repair and Surface Rebuilding
 > Water and Wastewater Protective Coating Systems | Article 11 of 24: Concrete Surface Preparation
 > Water and Wastewater Protective Coating Systems | Article 12 of 24: Steel Surface Preparation
 > Water and Wastewater Protective Coating Systems | Article 13 of 24: Moisture and Environmental Control
 > Water and Wastewater Protective Coating Systems | Article 14 of 24: Confined-Space Safety
 > Water and Wastewater Protective Coating Systems | Article 15 of 24: Selecting Lining Chemistries
 > Water and Wastewater Protective Coating Systems | Article 16 of 24: Potable-Water Infrastructure
 > Water and Wastewater Protective Coating Systems | Article 17 of 24: High-Build Wastewater Linings
 > Water and Wastewater Protective Coating Systems | Article 18 of 24: Resurfacers, Mortars, and Membranes
 > Water and Wastewater Protective Coating Systems | Article 19 of 24: Cracks, Joints, and Transitions
 > Water and Wastewater Protective Coating Systems | Article 20 of 24: Material Storage, Mixing, Plural-Component Equipment, and Application Planning
 > Water and Wastewater Protective Coating Systems | Article 22 of 24: Defects, Failure Analysis, and Coating Repairs
 > Water and Wastewater Protective Coating Systems | Article 24 of 24: Estimating, Closeout, Warranties, and Lifecycle Maintenance
 > Water and Wastewater Protective Coating Systems Course Assessment
 > Water and Wastewater Protective Coating Systems | Certificate of Completion Request